Area and volume calculators
8 area and volume calculators: room area, wall area and paint, roof area, circle and sector, triangle, pit volume, cylinder and stairs.
What this group solves
Area and volume sit under every take-off: floor area drives flooring, wall area drives paint and filler, roof area drives waterproofing and tiles, and circular areas drive pipe insulation and concrete. These tools are deliberately thin — pure geometry, no materials or workmanship — so they can sit at the front of any calculation chain.
Three things get missed repeatedly. Wall area must deduct openings but add the reveal: roughly 0.3-0.5 m² per door and 0.2-0.4 m² per window. Roof area is the plan area divided by cos(pitch), not a tape measure along the slope. And stairs need rise, going and number of risers checked together — residential 260-300 mm going and 150-175 mm rise is what the code expects.
This is the most-used group on the site and the one most exposed to convention: does wall area deduct openings, does room area deduct wall thickness, is roof area measured on plan or on the slope? Every answer depends on what the area is for — pricing, material take-off or load calculation all use different conventions, and the same element can differ by over 12% between them. Ask the purpose first, then pick the tool.
Which one for your case
| Room net area, wall area and ceiling area | Room Area Calculator |
| Wall area with door and window openings deducted | Wall Area and Paint Calculator |
| Roof area converted from plan to slope | Roof Area Calculator |
| Circle, sector, segment and annulus areas | Circle and Sector Calculator |
| Triangle area from three sides | Triangle Area Calculator |
| Pit or tank volume with side slopes | Battered Pit Volume Calculator |
| Cylinder, pipe and tank capacity | Cylinder Volume Calculator |
| Stair riser, going and flight length | Stair Calculator |
Where this group goes wrong
- Measuring rooms on centreline dimensions with no wall deduction. Deducting 240 mm each way turns a 3.6×4.2 room into 3.36×3.96 = 13.3 m², not 15.1 m² — 12% out, and flooring and paint are both over-ordered.
- Deducting all openings or none. The convention deducts individual openings over 0.3 m² and does not add reveal area; tenders often deduct everything and price reveals separately. The two approaches differ by about 5%.
- Reporting roof area on plan. At 30° the slope area is 1.155 times the plan, at 45° it is 1.414; flat roofs still carry a 2% structural fall, and membrane laps add another 10%.
- Mixing the three stair conventions. Concrete is sloped length × slab thickness, finishes are developed area, formwork is plan area — on one staircase those differ by more than 20%, so mixing them guarantees at least one wrong figure.