Earthwork calculators
Cut volume with side slopes and working space, backfill converted from compacted to loose volume, and compaction degree from field dry density and laboratory maximum.
What this group solves
Only three tools, but together they cover the whole cut-to-fill chain. Cut volume comes from the pit geometry, side slope and working space in bank cubic metres; backfill converts the required compacted volume into loose volume for buying or hauling; compaction checks whether the field sample passes. All three have to use the same conversion basis, or the argument about why a thousand cubic metres of excavation will not fill the hole never ends.
The key is three states: bank, loose and compacted. A typical soil bulks 1.30 when excavated and compacts to about 1.15 of its bank volume. So 1000 m³ bank comes out as 1300 m³ loose and compacts back to roughly 870 m³ — the difference is loss and settlement. Imported fill is bought by loose volume and accepted by compacted volume; mixing the two bases puts a 30% error straight into the order.
Only three tools here, yet this is the widest error band on the site. Take one pit and change the slope from 1:0.33 to 1:0.75 and the volume moves by more than 30%; leave 300 mm of working space off each side and a long pit loses hundreds of cubic metres. The right order is geometric convention first (does the bottom dimension include working space, where does depth start and end), then the slope, then the cut-and-fill balance for disposal.
Which one for your case
| Rectangular pit — excavation and disposal volumes | Earthwork Calculator |
| Volume already excavated — backfill and compaction | Backfill Volume Calculator |
| Roller passes or compaction factor | Compaction Degree Calculator |
| High water table — needs dewatering alongside | Wellpoint Dewatering Calculator |
Where this group goes wrong
- Measuring the pit bottom without working space. Footings need 300-800 mm each side (formwork face plus 300 where forms are used); on a 20×30 m pit, 500 mm a side is over 4% of the volume.
- Running depth from existing ground to the underside of blinding and forgetting blinding plus over-excavation. Permitted over-dig is usually 200-300 mm, while machine excavation often reaches 400 mm — and that is exactly what gets deducted at settlement.
- Guessing the slope ratio. Class I soil 1:0.33, class II 1:0.5, class III 1:0.75, class IV 1:1.0 for depths up to 5 m. One class out on a 10 m pit shifts the top width by 4 m.
- Setting backfill as cut minus footing volume with no bulking factor. Excavated soil is loose, and compacted backfill needs 10-15% more loose volume than its in-situ equivalent. Disposal is measured in situ, backfill in compacted terms — they cannot be subtracted directly.