M&E calculators
16 M&E calculators: cable sizing, voltage drop, circuit load and breaker, derated current capacity, lighting, water demand, pipe sizing, drainage falls, pump head, heat load, duct area and supports.
What this group solves
Building services take off along two chains. Electrical is a three-stage check — current capacity, then protection, then voltage drop; picking a cable size is not the end of it, because long runs usually fail on the 5% drop limit rather than on current. Plumbing and HVAC are flow, diameter, then resistance: supply pipe size from fixture units and diversity, drainage from discharge units subject to minimum falls.
The bulk of installation labour hides in supports and accessories: duct hangers spaced by duct width, tray brackets by span, pipe brackets by diameter and temperature. These invisible items routinely account for more than 30% of installation labour, so the tools here return bracket counts, steel weight and anchor counts instead of leaving it to guesswork.
M&E comes in discrete steps: conductor size, pipe diameter, duct size and drain slope are all picked from standard ranges, not calculated continuously. So the job is not precision, it is picking the right step and then checking it — ampacity passes, then check voltage drop; diameter fixed, check velocity; slope set, check the velocity ceiling. Skip a check and it comes back at inspection.
Which one for your case
| Sizing a conductor | Cable Size Calculator |
| Long runs — voltage drop check | Voltage Drop Calculator |
| Circuit load and breaker setting | Circuit Load and Breaker Calculator |
| Cable ampacity with installation derating | Cable Ampacity Derating Calculator |
| Fitting count and illuminance for a room | Lighting Level and Fixture Calculator |
| Supply pipe diameter from fixture units | Water Pipe Sizing Calculator |
| Drain diameter and slope | Drainage Pipe Slope Calculator |
| Pump head | Pump Head Calculator |
| Duct surface area and insulation | Duct Area Calculator |
Where this group goes wrong
- Sizing conductors on ampacity alone with no voltage-drop check. Beyond about 50 m the drop limit bites before the ampacity limit, terminal voltage falls below 95% of nominal, and motors struggle to start while lamps flicker.
- Reading ampacity straight from the table with no derating. Table values assume a single cable in air at 30 °C; in conduit ×0.8, multi-layer tray ×0.7, at 40 °C ×0.87. Multiply them together and you may have half the nominal figure.
- Believing a steeper drain slope always drains better. Above about 4 m/s the solids outrun the water and the pipe blocks more, not less — DN100 should sit between 12‰ and 20‰.
- Computing duct area and forgetting insulation. Insulated area is measured on the outside of the insulation; 30 mm on a 1000×320 duct adds roughly 15%, and the insulation itself is a separate line item.