Rebar calculators
19 rebar calculators: theoretical weight, anchorage length and modification factors, lap length, cutting length, spacing and bar count, stirrups, mesh, splice percentage, bend deduction and tendons.
What this group solves
Two chains run through this group: weight and length. The weight chain starts from theoretical weight (d²/162) and extends to mesh, slabs, rafts and chair bars up to total tonnage. The length chain starts at anchorage, passes through laps, hooks and bend deductions, and ends at cutting length and stock optimisation — a cutting error is not a small overrun, it is a whole batch of scrap.
Every length tool follows the code: basic anchorage length times the modification factor, then times the seismic factor. Lap length is anchorage times 1.2, 1.4 or 1.6 depending on the percentage spliced at a section. Each parameter line states which clause it comes from — read that line before changing a factor, because this is the highest-rework category on the site.
Rebar is the hardest account to reconcile, because drawings give shapes and bar marks, not weight. The chain runs: count bars and their lengths from the marks, correct the cut length for bend deduction, multiply by the theoretical mass per metre, then add laps, anchorage and mechanical joints. Any mismatch in convention shows up as tonnes — and rebar is one of the few materials where over-ordering ties up cash and under-ordering stops the job.
Which one for your case
| Diameter, length and count known — need tonnage | Rebar Weight Calculator |
| Looking up seismic anchorage length lae | Rebar Anchorage Length Calculator |
| Lap length where the stagger ratio is not 25% | Rebar Lap Length Calculator |
| Cut lengths that must allow for 90° and 135° bend deduction | Rebar Bend Deduction Calculator |
| Estimating a whole slab or raft mat | Raft Foundation Rebar Calculator |
| Checking whether the reinforcement ratio is adequate or over-reinforced | Reinforcement Ratio Calculator |
| Planning cuts against 9 m or 12 m stock lengths | Rebar Stock Cutting Calculator |
Where this group goes wrong
- Cutting to the straight dimension on the drawing. Every 90° bend takes 2d of bend deduction, so a 12 m beam bar with two hooks is over-counted by about 0.2 m; a few hundred bars a floor adds up to tonnes of phantom steel.
- Reading the lap length straight from la and forgetting the stagger factor. At 50% lapped in one section multiply by 1.4, at 100% by 1.6, and never less than 300 mm. Miss this and the joint zone comes up 30% short.
- Taking stirrup length as the member perimeter. A 300×600 beam with 25 mm cover and Φ8 stirrups cuts at (300-50+600-50)×2 plus hooks — over 200 mm less than the perimeter. With dozens of stirrups per beam the error easily reaches 10%.
- Substituting d in centimetres into d²/162. The formula takes d in millimetres: Φ12 gives 0.888 kg/m. Using centimetres gives 88.8 kg/m, out by a factor of 100.