# Climbing Scaffold Calculator (Attached Lifting)

Enter the perimeter and storey height to get masts, frame height, standards and decking.

- Page: https://jianzhujisuan.com/en/climbing-scaffold
- Category: Temporary Works (https://jianzhujisuan.com/en/c/temporary-works)
- Chinese version: https://jianzhujisuan.com/zh/climbing-scaffold.md
- Data checked: 2026-10-25

## Quick result

With the default inputs (Building length 30 m, Building width 16 m, Storey height 3.0 m, Floors covered 4.5 levels, Mast spacing 4.5 m, Standard spacing 2.0 m, Lift height 1.8 m, Frame width 0.9 m, Total storeys 18 levels): **Lifting masts 21 pcs**

Frame height 13.5 m over 4.5 floors; 1242 m² of facade, only 14% of the floor area

## Inputs

| Parameter | Type | Default | Unit | Note |
|---|---|---|---|---|
| Building length | number | 30 | m | The frame runs right round the building; the perimeter is worked out from length and width |
| Building width | number | 16 | m | Short side; together with the length it sets the perimeter and the number of masts |
| Storey height | number | 3.0 | m | Structural storey height, not clear height |
| Floors covered | number | 4.5 | levels | Frame height = floors covered x storey height. Code caps it at five storeys; 4.5 is the usual layout |
| Mast spacing | number | 4.5 | m | Centre-to-centre spacing of lifting masts. A closed loop always turns a corner, so the 5.4 m kinked-run limit applies; 3.0-4.5 is usual |
| Standard spacing | number | 2.0 | m | Usually 1.5 or 2.0, 2.0 maximum; each mast must land on a standard |
| Lift height | number | 1.8 | m | Decking goes in at every lift; 1.8 is usual for all-steel frames |
| Frame width | number | 0.9 | m | Clear distance between the inner and outer rows. Code caps it at 1.2 m; 0.6 or 0.9 is usual |
| Total storeys | number | 18 | levels | Used only for the gross floor area, so quoted rates per floor area can be checked |

## Formula

- **Perimeter**: P = 2 x (length + width)
- **Frame height**: H = floors covered x storey height, with H within five storeys and H x mast spacing within 110 m2
- **Masts**: N = perimeter / mast spacing, rounded up
- **Standards**: count = perimeter / standard spacing x 2 rows, length = count x H
- **Lifts**: n = H / lift height rounded up; decking = P x frame width x n
- **Ledgers**: length = 2 x P x n, one inner and one outer per lift
- **Facade protection**: area = P x H; guide rail length = masts x H

## Worked example

A 30 x 16 m building at 3.0 m storeys covering 4.5 floors with 4.5 m mast spacing: perimeter 92 m, frame height 13.5 m, 21 masts, 92 standards, eight lifts at 1.8 m, 662 m2 of decking, 1242 m2 of facade protection, 1472 m of ledgers and 284 m of guide rail. The same building at 18 storeys has 8640 m2 of floor area, so the facade is only 14% of it.

## Questions

### How many lifting masts does a climbing scaffold need?

Divide the perimeter by the mast spacing and round up, not to nearest. A 30 x 16 m building has a 92 m perimeter, so at 4.5 m spacing it needs 21 masts; 20 would only allow 4.6 m each. The code sets only upper limits: 7.0 m on straight runs and 5.4 m on kinked or curved runs, with 3.0-4.5 m usual on site. Tighter spacing means more masts, lower load per mast, but more hoists and wall ties, so the cost goes up.

### Is climbing scaffold hired by floor area or by facade area?

By facade protection area, or by mast-month, never by floor area. The two differ widely: a 30 x 16 m, 18-storey building has 8640 m2 of floor area but only 1242 m2 of facade, a factor of seven. At the same unit rate a floor-area quote is 259k against 37k on facade area, and the gap is not price, it is the wrong denominator. Fix the denominator in the contract before arguing price: facade area (perimeter x frame height) or lift area (perimeter x lift height x number of lifts).

### Why is the frame limited to five storeys?

JGJ 202-2010 caps the frame height at five storeys, the product of frame height and mast span at 110 m2, and the frame width at 1.2 m. All three are mandatory. The reason is straightforward: a taller frame over a wider span carries a bigger overturning moment from wind and eccentric load, and all of it has to go into the structure through the wall ties. So more covered floors forces tighter mast spacing: at five floors of 3 m the 110 m2 rule caps the span at 7.3 m, which in practice means 7.0 m on straight runs and 5.4 m on kinked runs.

### How does a climbing frame compare with a traditional tube-and-fitting scaffold per square metre?

They are not the same quantity, so a per-square-metre comparison is meaningless. A ground-based scaffold is priced on protection area at 21.4 kg of tube per square metre (27.0 kg including couplers), and the whole lot goes up at once. A climbing frame is mostly masts, guide rails and decking, and the same set climbs dozens of floors. Ask how many masts and how many climbs instead. To compare at all, put both on the same denominator, cost per square metre of floor area built: the ground-based figure grows with the number of storeys while the climbing figure barely does.

## Related tools

- [Scaffolding Calculator](https://jianzhujisuan.com/en/scaffolding): Enter the scaffolded length and height (plus the second side for four sides) to get the area, tube, coupler and board quantities.
- [Formwork Turnover Calculator](https://jianzhujisuan.com/en/formwork-turnover): Initial formwork area and replacement allowance from total area and cycles.
- [Full Scaffold Material Calculator](https://jianzhujisuan.com/en/full-scaffold): Standards, tube length and weight, couplers and board area.
- [Formwork Lateral Pressure Calculator](https://jianzhujisuan.com/en/formwork-pressure): Smaller of the two GB 50666 Annex A.0.4 expressions, plus head and critical rate.
- [Scaffold Tie Calculator](https://jianzhujisuan.com/en/scaffold-tie): Tie count from perimeter and height, with spacing limits checked.
- [Scaffold Dismantle Sequence Calculator](https://jianzhujisuan.com/en/scaffold-dismantle): Lifts to strip, allowable step height, and where the raking props start.

---

Generated by BuildCalc. All calculations run in your browser; no data is uploaded. Formulas follow national standards and common trade practice; local codes govern.