# Site Mix Adjustment Calculator

Enter the lab mix and moisture content to get real batch weights.

- Page: https://jianzhujisuan.com/en/concrete-water-adjust
- Category: Concrete (https://jianzhujisuan.com/en/c/concrete)
- Chinese version: https://jianzhujisuan.com/zh/concrete-water-adjust.md
- Data checked: 2026-10-25

## Quick result

With the default inputs (Cement (lab) 340 kg/m³, Sand (dry) 700 kg/m³, Gravel (dry) 1200 kg/m³, Water (lab) 180 kg/m³, Sand moisture 3%, Gravel moisture 1%, Cement per batch (50 kg bags) 2 bags): **Water to add per m³ 147.0 kg/m³**

## Inputs

| Parameter | Type | Default | Unit | Note |
|---|---|---|---|---|
| Cement (lab) | number | 340 | kg/m³ |  |
| Sand (dry) | number | 700 | kg/m³ |  |
| Gravel (dry) | number | 1200 | kg/m³ |  |
| Water (lab) | number | 180 | kg/m³ |  |
| Sand moisture | number | 3 | % |  |
| Gravel moisture | number | 1 | % |  |
| Cement per batch (50 kg bags) | number | 2 | bags |  |

## Formula

- **Wet sand = dry sand × (1 + moisture)**: same for gravel
- **Water added = lab water − dry sand×m − dry gravel×m**: keeps w/b constant
- **Batch weight = per m³ × (cement per batch ÷ cement per m³)**: batch sized to whole bags

## Worked example

C30 lab mix: cement 340, sand 700, gravel 1200, water 180 kg/m³; sand 3% and gravel 1% moisture. Wet sand 721, wet gravel 1212 kg, aggregate brings 33 kg of water, so add only 147 kg. For a two-bag (100 kg) batch the factor is 0.294: sand 212 kg, gravel 356 kg, water 43 kg.

## Questions

### Why not just follow the lab mix and add water as needed?

Water/binder ratio governs strength. Adding water without deducting what the aggregate already carries raises w/b by a real margin - roughly 20 kg extra water per cubic metre costs 3-5 MPa - and promotes bleeding and cracking. Always solve for water first.

### How often should moisture be measured, and what about rain?

Once per shift normally, every two hours after or during rain, sampling surface and core separately. The top 10 cm of an open sand pile can run 3-5 points wetter than the core; sampling only the surface over-deducts water and the mix comes out dry.

### The calculated water comes out negative - what is wrong?

Three usual causes: the lab water figure assumed a superplasticiser that is not being added on site; the moisture reading is too high (often free water on the sample after rain); or a decimal slip in the aggregate weights. Check moisture first, then the admixture dose.

## Related tools

- [Concrete Volume Calculator](https://jianzhujisuan.com/en/concrete-volume): Enter length, width and thickness to get the concrete volume you need and how many truck loads that is.
- [Formwork Area Calculator](https://jianzhujisuan.com/en/formwork-area): Pick a member type, enter section and length, and get the formwork contact area plus sheet and batten estimates.
- [Concrete Mix Design Calculator](https://jianzhujisuan.com/en/concrete-mix-ratio): Work out cement, sand, gravel and water per cubic metre from the target grade and water-cement ratio.
- [Cement Quantity Calculator](https://jianzhujisuan.com/en/cement-quantity): Get total cement, bag count and the cement/fly-ash split for a given volume and grade.
- [Concrete Pour Sequencing Calculator](https://jianzhujisuan.com/en/concrete-pour-plan): Divide a slab into strips and get the volume, truck count and duration for each pour.
- [Concrete Strength Converter](https://jianzhujisuan.com/en/concrete-strength-convert): Convert between grade, MPa, psi and kgf/cm², with cube-to-cylinder correction.

---

Generated by BuildCalc. All calculations run in your browser; no data is uploaded. Formulas follow national standards and common trade practice; local codes govern.