# Formwork Over-Height Calculator

Enter the support height and formwork contact area to get the over-height formwork quantity under the beam/slab and column/wall rules.

- Page: https://jianzhujisuan.com/en/formwork-superhigh
- Category: Concrete (https://jianzhujisuan.com/en/c/concrete)
- Chinese version: https://jianzhujisuan.com/zh/formwork-superhigh.md
- Data checked: 2026-10-25

## Quick result

With the default inputs (Member type Slab (horizontal), Support height 5.3 m, Formwork contact area 100 m²): **Over-height formwork 100.00 m²**

At 9.6 m with 100 m² of formwork: a slab counts 200 m², a column only 93.75 m²

## Inputs

| Parameter | Type | Default | Unit | Note |
|---|---|---|---|---|
| Member type | select | Slab (horizontal) | — |  |
| Support height | number | 5.3 | m | Not the storey height: slabs to the soffit (storey height minus slab thickness), beams to the beam soffit, columns and walls to the top of the member |
| Formwork contact area | number | 100 | m² | Paste the figure from the formwork area calculator; sum several members first |

## Formula

- **Threshold**: Applies only above a 3.6 m support height
- **Steps (beams, slabs)**: n = ⌈(support height − 3.6) ÷ 3⌉, part steps round up
- **Quantity (beams, slabs)**: A = full contact area × n
- **Steps (columns, walls)**: 3.6-6.6 m = 1, 6.6-9.6 m = 2, 9.6-12.6 m = 3 ...
- **Area per segment**: Aᵢ = full contact area × segment height ÷ support height
- **Quantity (columns, walls)**: A = Σ(Aᵢ × steps of that segment)
- **Excluded members**: Tie columns, ring beams, large steel-panel walls

## Worked example

A 100 m² slab under a 5.40 m storey with a 100 mm slab: support height 5.30 m, 1.70 m over, one step, so 100.00 m² of over-height formwork. Four 500×500 columns at the same storey have 43.20 m² of formwork: 1.80 m over, measured on that band only at 14.40 m² — taking the full height times one step would give 43.20 m², over by 28.80 m².

## Questions

### Where does over-height formwork start? Is 3.6 m the storey height or the support height?

It is the support height of 3.60 m, not the storey height and not the clear height. Measure to the slab soffit for slabs (storey height minus slab thickness), to the beam soffit for beams (storey height minus beam depth), and to the top of the member for columns and walls. A 5.40 m storey with a 100 mm slab has a 5.30 m support height; in a beam-and-slab floor the beam soffit may sit at only 5.40 − 0.70 = 4.70 m. Using the storey height overstates it, using the clear height understates it.

### Why do beams and slabs take the full area while columns and walls take only the band above 3.6 m?

Because the support works differently. Beams and slabs are horizontal, carried on a full grid of props: raise the floor and every prop is extended and extra ledgers added, including below 3.6 m, so the quantity is the full contact area times the number of steps. Columns and walls are vertical, their side forms built up lift by lift: the support below 3.6 m is unchanged and only the lifts above receive extra bracing, so each segment area is counted with its own step multiplier. At 9.6 m with 100 m² of formwork, a slab is measured at 200.00 m² and a column at only 93.75 m² — one is double the contact area, the other is below it.

### How are the steps counted? Is 1.8 m over already one step?

Yes. Part steps round up: for beams and slabs n = ⌈(support height − 3.6) ÷ 3⌉, so anything from 0.1 m to 3.0 m over is one step and 3.1 m over is two. For columns and walls the bands are 3.6-6.6 m for the first step, 6.6-9.6 m for the second, 9.6-12.6 m for the third. That makes 6.60 m exactly one step and 6.61 m two — one centimetre at the threshold doubles the quantity.

### Do tie columns and ring beams attract over-height formwork?

No. Tie columns, ring beams and large steel-panel walls are expressly excluded from over-height formwork, because their support does not rise with the storey. This is the easiest item to over-claim across a whole building: a 30-storey block has 200-400 tie columns, and counting each as over-height inflates the total substantially. Wall and slab construction joints are the opposite case — their over-height is added into the corresponding wall or slab quantity, never listed separately.

### Are the 3.6 m, 5 m and 8 m thresholds the same thing?

No — three lines, three different purposes, none replacing another. 3.6 m is the pricing line: above it, over-height formwork is paid separately. 5 m is the hazardous-works line (MOHURD circular 31 of 2018): a support height of 5 m or more, or a span of 10 m or more, or a total load of 10 kN/m² or more, or a line load of 15 kN/m or more — any one triggers a dedicated method statement. 8 m is the expert-review line: 8 m or more in height, or an 18 m span, or 15 kN/m², or 20 kN/m, and a panel must be convened. A 4.5 m storey therefore attracts over-height formwork but is not yet hazardous works, while an 8.5 m storey needs both the money and the panel.

## Related tools

- [Concrete Volume Calculator](https://jianzhujisuan.com/en/concrete-volume): Enter length, width and thickness to get the concrete volume you need and how many truck loads that is.
- [Formwork Area Calculator](https://jianzhujisuan.com/en/formwork-area): Pick a member type, enter section and length, and get the formwork contact area plus sheet and batten estimates.
- [Concrete Mix Design Calculator](https://jianzhujisuan.com/en/concrete-mix-ratio): Work out cement, sand, gravel and water per cubic metre from the target grade and water-cement ratio.
- [Cement Quantity Calculator](https://jianzhujisuan.com/en/cement-quantity): Get total cement, bag count and the cement/fly-ash split for a given volume and grade.
- [Concrete Pour Sequencing Calculator](https://jianzhujisuan.com/en/concrete-pour-plan): Divide a slab into strips and get the volume, truck count and duration for each pour.
- [Concrete Strength Converter](https://jianzhujisuan.com/en/concrete-strength-convert): Convert between grade, MPa, psi and kgf/cm², with cube-to-cylinder correction.

---

Generated by BuildCalc. All calculations run in your browser; no data is uploaded. Formulas follow national standards and common trade practice; local codes govern.