算BuildCalc

Rebar weight table

Every bar size from 6 mm to 40 mm: kg per metre, weight per 9 m and 12 m bar, metres per tonne.

BarWeight (kg/m)9 m bar (kg)12 m bar (kg)Metres per tonne
Φ60.2222.002.664505
Φ6.50.2602.343.123846
Φ80.3953.564.742532
Φ100.6175.557.401621
Φ120.8887.9910.661126
Φ141.2110.8914.52826
Φ161.5814.2218.96633
Φ182.0018.0024.00500
Φ202.4722.2329.64405
Φ222.9826.8235.76336
Φ253.8534.6546.20260
Φ284.8343.4757.96207
Φ326.3156.7975.72158
Φ367.9971.9195.88125
Φ409.8788.83118.44101

All values are computed from the stated formulas; ranges show the usual spread. Use measured data or the local code where it differs.

How to use this table

Common misuse

Calculate the actual number

Other reference tables

FAQ

How do I calculate rebar weight per metre?
0.00617 × diameter², i.e. d²/162. That is 0.888 kg/m for 12 mm and 3.85 kg/m for 25 mm.
How many metres of 12 mm bar in a tonne?
1000 ÷ 0.888 ≈ 1126 m, or 125 lengths of 9 m and 94 lengths of 12 m.
Why does theoretical weight differ from the weighbridge?
Theoretical weight uses 7850 kg/m³ and nominal dimensions; ribs, rolling tolerance and corrosion shift the real figure by 1-4%.
How far can actual mass deviate from theoretical?
GB/T 1499.2 permits ±7% for Φ6-Φ12, ±5% for Φ14-Φ20 and ±4% for Φ22-Φ50. A delivery 4-7% light is therefore compliant, and a claim on that difference will not stand.
How is strand mass per metre calculated?
From nominal area for 1×7 standard strand: Φ15.2 is 140 mm² at 1.101 kg/m, Φ12.7 is 98.7 mm² at 0.775 kg/m and Φ17.8 is 191 mm² at 1.50 kg/m. Do not use d²/162 — that formula only applies to hot-rolled bar.
How is the percentage of lapped bars calculated?
Within one connecting zone (1.3 times the lap length), lapped bar area ÷ total bar area. In tension zones of beams and slabs it should not exceed 25%, and 50% in compression; beyond that the code applies a lap length multiplier.
Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.