Asphalt Quantity Calculator
Area × thickness × density gives tonnage, then bitumen content.
Quick answer
With the default inputs: Pavement area 10000 m² · Compacted thickness 0.05 m · Mix bulk density 2.4 t/m³ etc.Bitumen required 58.29 t
Edit the inputs below to recalculate.Inputs
Result
Bitumen required
58.29t
| Pavement area | 10000m² |
| Compacted thickness | 50mm |
| Net mix weight | 1200.0t |
| Mix with waste | 1224.0t |
| Bitumen | 58.29t |
| Aggregate | 1165.7t |
| Bitumen content of mix | 4.76% |
| Bitumen per m² | 5.83kg/m² |
| Mix per m² | 0.122t/m² |
| 30 t truck loads | 41loads |
Bitumen ratio and bitumen content are different numbers and this is where asphalt take-offs most often go wrong. Ratio = bitumen ÷ aggregate (denominator excludes bitumen); content = bitumen ÷ total mix. A 5% ratio equals 4.76% content — a 0.24 point difference worth tens of tonnes on a big job. Designs quote ratio, test reports quote content; never substitute one for the other. Use bulk density, not maximum theoretical: about 2.40 for AC-13 and 2.42 for AC-20. Thickness is compacted; loose depth needs a 1.15-1.25 factor.
Formula
| Net mix weight | M = area × thickness × density |
| With waste | M = M × (1 + waste) |
| Bitumen | G = M × ratio ÷ (100 + ratio) |
| Aggregate | G = M − bitumen |
| Bitumen content | content = bitumen ÷ M × 100% |
10000 m² at 50 mm compacted, 2.4 t/m³, 5% bitumen ratio and 2% waste: 1200.0 t net mix, 1224.0 t with waste, 58.29 t of bitumen, 1165.71 t of aggregate, 4.76% content and 5.83 kg of bitumen per square metre.
FAQ
What exactly differs between ratio and content?
The denominator. Ratio = bitumen ÷ aggregate, excluding bitumen; content = bitumen ÷ total mix, including it. So the ratio number is always larger. 5% ratio equals 4.76% content; 6% equals 5.66%. Mix designs quote ratio because plants add bitumen to aggregate; extraction tests report content because that is what they measure. Always convert when comparing, or the lot fails.
Why bulk density rather than maximum theoretical?
Because you are weighing the material that actually goes on the road — compacted, with voids. Bulk density accounts for those voids, about 2.40 t/m³ for AC-13. Maximum theoretical density assumes zero voids, around 2.50, and would overstate the tonnage by roughly 4%. It is used only to derive air voids (VV), never for weight.
How is the loose-depth factor used?
Loose depth = compacted depth × 1.15-1.25. The paver sets screed height to the loose depth and rollers bring it down to design thickness. The factor depends on mix and compaction: coarser mixes and SMA take the higher value, fine-graded the lower, and under-rolling pushes it higher. Note that material quantities use compacted thickness — using loose depth would overstate the tonnage by 15-25%.
Related calculators
Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.