Backfill Volume Calculator

Backfill volume, soil required, surplus to remove and truck loads.

Inputs

m
m
m
m³
Volume taken by footings, pile caps and basement
Loose-to-natural factor, usually 1.1-1.3
Compacted-to-natural ratio, usually 1.02-1.08
m³

Result

Formula

Pit volumeV = length × width × depth
BackfillV = pit − structure
Natural soilV = backfill ÷ Ks′
Loose volumeV = natural × Ks
SurplusV = pit − natural
TrucksN = ceil(loose ÷ capacity)
A 10 × 8 × 3 m pit with 80 m³ of structure, Ks 1.20, Ks′ 1.05 and 12 m³ trucks: 160.00 m³ of backfill needs 152.38 m³ of natural soil (182.86 m³ loose), leaving 87.62 m³ surplus — 105.14 m³ loose, or 9 loads.

FAQ

What exactly are the bulking factors?
Natural soil is compacted in situ; digging loosens and expands it, and that ratio is Ks (loose ÷ natural), typically 1.1-1.3. Recompacted soil shrinks back but not exactly to the original, giving Ks′ (compacted ÷ natural), usually 1.02-1.08. Cart-away volumes use loose figures, backfill uses compacted — mixing them costs about 20%.
Why backfill in layers?
Compaction energy only reaches a limited depth. A thick lift stays loose at the bottom, and later settlement drags everything above it down, cracking slabs and shearing pipes. Codes require layers no more than 300 mm loose, each compacted and tested before the next. This is the commonest source of failures.
What if the surplus comes out negative?
That means the excavated soil is insufficient and soil must be imported — common with deep pits, small structure volumes or where good fill is specified. Note that site storage is limited, so surplus is often carted away and later bought back; the double haul usually costs more than the soil, so balance on site where possible.