Earthwork Calculator

Enter pit dimensions and slope ratio to get cut volume, backfill and spoil to remove.

Inputs

m
For a trench, enter trench length
m
Include working space; for a trench use bottom width
m
m³
Footing, blinding and equipment bases left in the pit

Result

Formula

Rectangular pit (prismoid)V = H/6 × [ab + (a+2mH)(b+2mH) + 4(a+mH)(b+mH)]
TrenchV = (B + mH) × H × L
BackfillV_back = V_cut − structure volume
Loose volumeV_loose = V_spoil × 1.3
A 10×6 m pit 3 m deep with 1:0.33 batter and a 30 m³ structure: 231.4 m³ cut, 201.4 m³ of backfill once compacted, needing 223.8 m³ of bank soil — 7.6 m³ of spoil, 9.9 m³ loose, one 15 m³ truck load.

FAQ

How do I choose the slope ratio?
By soil type: 1:0.5 to 1:1 for sand and fill, 1:0.33 to 1:0.5 for silt and ordinary clay, 1:0.33 for stiff clay. Pits deeper than 5 m normally need shoring rather than battering, and any pit with groundwater above the base must be dewatered first.
What is the difference between bank, loose and compacted volume?
Bank volume is undisturbed soil and is the basis for measurement and payment. Loose volume is what it becomes after digging, about 1.25-1.35 times larger, and is what trucks are rated in. Compacted volume is smaller than bank volume, so backfill quantities are multiplied by roughly 1.15. Mixing these up doubles or halves your haulage cost.
Should working space be included?
Yes. Formwork and access need room, typically 300-800 mm on each side: 300 mm for formwork on concrete footings, 800 mm where a waterproof membrane is applied, plus more for drainage trenches. Enter bottom dimensions that already include working space.