Backfill Volume Calculator
Backfill volume, soil required, surplus to remove and truck loads.
With the default inputs: Pit length 10 · Pit width 8 · Pit depth 3 etc.Compacted backfill 160.00 m³
Edit the inputs below to recalculate.Inputs
Result
| Excavation volume | 240.00m³ |
| Structure volume | 80.00m³ |
| Natural soil required | 152.38m³ |
| Loose volume to import | 182.86m³ |
| Surplus (natural) | 87.62m³ |
| Surplus to cart away | 105.14m³ |
| Truck loads out | 9loads |
| Truck loads in | 0loads |
Backfill is compacted in layers no more than 300 mm loose, to the specified density (typically 0.93-0.96). Ks and Ks′ should be measured; they vary widely by soil type, and sand and clay must not be mixed.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Pit volume | V = length × width × depth |
| Backfill | V = pit − structure |
| Natural soil | V = backfill ÷ Ks′ |
| Loose volume | V = natural × Ks |
| Surplus | V = pit − natural |
| Trucks | N = ceil(loose ÷ capacity) |
How to work it out
- Take the compacted volume needed: pit volume less foundations, blinding and basement structure.
- Deduct what is not backfilled — the working space is only outside the footing, and internal fill is measured to the underside of the slab.
- Convert compacted to loose using the bulking factor: loose ≈ compacted × 1.30 for ordinary soil.
- Work out the number of layers from loose thickness per layer (200-300 mm); tighter compaction targets mean more layers.
- Separate imported fill from re-used arisings — re-use only needs handling, imported fill is bought by loose volume.
Where it goes wrong
- Forgetting to deduct footings and blinding — one large pile cap displaces tens of cubic metres, so treating it as fill buys soil you do not need.
- Mixing compacted and loose bases — a 30% error, either short or unreturnable surplus.
- Planning a single lift — trenches with services or waterproofing must be layered at 200-300 mm, with hand compaction where machines cannot reach.
Material and cost
Imported fill runs 30-60 per m³ loose including haulage, with distance the dominant variable; re-handling arisings is 8-20 per m³ and layered compaction labour 15-30 per m³. Raising the compaction target from 0.90 to 0.94 can add 30% to plant hours. A good cut-and-fill balance with stockpiling on site removes the import entirely — that is the biggest lever in earthworks cost.
On site
- Stockpile good excavated material close by and keep it separate from demolition debris; once mixed it can only go to tip.
- Pump out standing water and clear debris before filling — saturated soil will not reach the target density.
- Test density layer by layer, not at the end, when the only remedy is digging it back out.
Basis
- GB 50202-2018 Standard for acceptance of building foundation works, Chapter 9 (earthwork)
- JGJ 79-2012 Technical code for ground treatment of buildings (compaction and testing)
- GB 50300-2013 Unified standard for construction quality acceptance
FAQ
What exactly are the bulking factors?
Why backfill in layers?
What if the surplus comes out negative?