High Strength Bolt Torque Calculator

Preload by size and class, with snug and final torque.

Quick answer

With the default inputs: Bolt size M20 · Property class 10.9S · Torque coefficient K 0.13Final torque 443 N·m

Edit the inputs below to recalculate.

Inputs

0.110-0.150 for hex head, use the batch test value

Result

Final torque
443N·m
Design preload155kN
Construction preload (1.1P)171kN
Nominal diameter20mm
Torque coefficient0.130
Snug torque (0.5T)222N·m
Final torque443N·m
Inspection torque (1.1T)488N·m
Estimated preload at snug85kN
Bolt shank mass (1.1d long)0.054kg

Final torque is T = K × Pc × d with Pc = 1.1P, and K must be the batch test value, not a rule of thumb — moving K from 0.11 to 0.15 changes the preload by 27% at the same torque. Tension control bolts rely on shearing the splined end rather than a torque figure, but preload still applies. Slip factors for the faying surfaces must be tested batch by batch.

Formula

Final torqueT = K × P × d
Snug torque0.5T
Inspection torque1.1T
Construction preload1.1P
Meaning of KShare of torque lost to thread and bearing friction
UnitsP in kN and d in mm gives N·m directly
M20 10.9S at K = 0.13: 155 kN design preload, 171 kN construction preload, 443 N·m final torque, 222 N·m snug and 488 N·m inspection.

Preload and final torque for high strength hex bolts at K = 0.13

Size8.8S preload kN8.8S torque N·m10.9S preload kN10.9S torque N·m
M1680166100208
M20125325155403
M22150429190543
M24175546225702
M272308072901018
M3028010923551385

How to work it out

  1. Look up the pretension P for the size and property class: an M20 10.9S bolt takes 155 kN and 8.8S takes 125 kN. These are code values, not calculations.
  2. Part-turn first: the initial pass is 50% of the final torque, to close the pack and remove gaps. For a hex bolt it is roughly 0.065 × P × d.
  3. Then final torque Tc = K × P × d, with K the torque coefficient (0.110-0.150, 0.13 nominal) and d the nominal diameter in metres.
  4. For M20 10.9S: 0.13 × 155 × 0.020 = 0.403 kN·m, that is 403 N·m.
  5. Verify by torque check on 10% of bolts within ±10%; for tension-control bolts the splined end must shear off instead and no torque check is made.

Where it goes wrong

Material and cost

10.9S M20 × 60 assemblies 8-15 CNY each, 8.8S 5-10, tension-control 20-30% more. Installation 3-8 CNY per bolt, torque wrench hire 100-300 CNY per day.

On site

Basis

FAQ

Why not just tighten until it stops?
Because a high strength bolt works by clamping the plates so friction carries the load, not by shear in the shank. Under-tighten and the joint slips; once slipped the bolts bear in shear, capacity collapses and the movement is permanent. Codes require snug, re-snug and final passes so the faying surfaces close progressively — one pass to final torque loses about 20% of preload closing the gaps.
Why must K be measured?
Because K depends on thread accuracy, surface treatment and lubrication, and batches from different makers differ by up to 30%. Codes require eight torque coefficient tests per batch and the mean value used. A wrong K goes straight into preload: assuming 0.13 when the truth is 0.15 under-tightens by 13%, and the joint slips then loosens under fatigue. This is why bolt, nut and washer must come from the same batch.
Tension control or hex head?
Tension control bolts are run until the splined end shears off, at which point preload is reached — no torque control, little operator error, but single use and inspection is visual. Hex head bolts use the torque method, can be re-tightened, but need K testing, three passes and torque checks. Long-span and industrial work in China favours tension control; joints that get dismantled favour hex head.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. High Strength Bolt Torque Calculator. 2026-10-25. https://jianzhujisuan.com/en/bolt-torque

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.