Bored Pile Calculator

Concrete, overbreak and rebar cage weight for bored piles in one go.

Also known as drilled shaft · bored cast in situ pile · rotary bored pile

Quick answer

With the default inputs: Pile diameter 800 mm · Pile length 30 m · Number of piles 10 pcs etc.Total concrete 165.9 m³

Use your own dimensions ↓

Inputs

pcs
%
Laitance to trim, usually 5-15%
pcs

Result

Total concrete
165.9m³
Section area0.5027m²
Concrete per pile (with overbreak)16.59m³
Main bar unit weight2.468kg/m
Total cage weight8.88t
Average reinforcement ratio54kg/m³
How this is worked out

Bored piles are cast under slurry, so laitance and slurry mix into the top and base; the top length is trimmed off, hence a 1.05-1.15 overbreak factor on concrete. Main-bar weight uses the empirical m = d²×0.00617 (d in mm), standard for HRB400 ribbed bar. The cage total counts main bars only - stirrups, stiffening rings and spacers add about 8-12%. Typical reinforcement is 60-120 kg/m³; if the ratio looks way off, recheck bar count and diameter.

Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator

Formula

Section areaA = πD²/4
Concrete per pileV₁ = A·L·(1+overbreak%)
Total concreteV = V₁·n
Main bar unit weightm = d²×0.00617 (kg/m)
Cage weightW = m·L·bars·piles / 1000 (t)
800 mm × 30 m, 10 piles, 10% overbreak: 16.6 m³ per pile, 166 m³ total; Φ20 × 12 bars at 2.468 kg/m gives about 8.9 t of cage, ~54 kg/m³.

Quantities per metre by diameter (from this page's formulas, 10% overbreak, 12 × 20 mm bars)

Diameter (mm)Section area (m²)Concrete (m³/m)Cage (kg/m)30 m pile (m³)
6000.2830.31129.69.33
8000.5030.55329.616.59
10000.7850.86429.625.92
12001.1311.24429.637.32
15001.7671.94429.658.32
20003.1423.45629.6103.67

Choosing the drilling method (typical conditions, not code limits)

MethodGround it suitsBelow water tableSupportTypical diameter (mm)Main cost
Rotary auger (spin rig)Cohesive soils, silt, sand, gravel at moderate NYes, with slurry or casingSlurry / full casing600-2000Large spoil volume, needs a hard standing
Rotary drilling (direct / reverse circulation)Clay, silt, fine to medium sandYesSlurry600-1600Slow; reverse circulation cleans the base better
Percussion / chiselCobbles, boulders, weathered rockYesSlurry600-1500Good rock penetration but slow
Continuous flight auger (dry)Cohesive soils and silt above the water tableNot suitable (fails below water)None400-800No slurry and fast, but fails the moment water appears
Full casing (oscillator / rotator)Unstable ground, collapse-prone holes, next to existing buildingsYes (dry inside the casing)Steel casing800-1500Expensive and heavy, but no slurry and no vibration

Basis

FAQ

What overbreak allowance should I use?
The laitance at the pile top is trimmed, usually 0.5-1.0 m, i.e. a factor of 1.05-1.15. Longer piles and longer hole-open times mean more settlement and a higher allowance. Tremie concrete has its own overbreak on top. Default is 10%; allow 15% for poor ground or deep piles.
Why does the cage weight only count main bars?
Main bars make up over 85% of the cage and dominate material and pricing. Stirrups, stiffening rings and spacers are small-diameter, distributed items - add 8-12% of the main bars. If the reinforcement ratio falls outside 60-120 kg/m³, recheck bar count and diameter.
Why overpour bored piles, and by how much?
The hole is held open with slurry and the concrete is poured from the bottom up, so the top of the column mixes with slurry and laitance and has to be broken off. Practice is to overpour 0.5-1.0 m, or to apply a 1.05-1.15 factor to the concrete volume. That overpour is sunk cost and must be in the quote, otherwise it comes out of your margin at settlement. The actual height is set by the trial pile and the local code - this tool only leaves you the factor to fill in.
What reinforcement ratio is normal for a bored pile?
Typically 60-120 kg/m³ of pile volume. Small friction piles sit at the low end; large diameters and piles taking lateral load or seismic detailing sit high. If your figure is well under 60, check the bar count and diameter first; well over 120, check whether you have counted stiffening rings and sonic logging tubes. This tool counts main bars only - stirrups, rings and spacers add roughly 8-12%.
Can this tool work out the pile capacity?
No, and it should not be used for that. It totals materials only: concrete volume and cage weight. Capacity depends on the ground investigation parameters, the bearing stratum, shaft friction, the construction method and the trial pile results; the designer must calculate it to JGJ 94 or the local code and prove it with a static load test. Treating a take-off as a capacity figure is how structural failures happen.
How do I reconcile concrete against the client after trimming the pile top?
Keep two figures. The design volume (drawing length times section area) is what you bill. The poured volume, including overpour and overbreak, is what you reconcile against the ready-mix supplier and what the concrete actually costs. The gap is the overpour loss, usually 5-15%. Never bill the poured volume and never cost the design volume - the two are different measurements and mixing them loses money on one side or the other.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Bored Pile Calculator. 2026-10-25. https://jianzhujisuan.com/en/bored-pile

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.