算BuildCalc

Brick Wall Calculator

Pick a wall thickness, enter length and height, deduct openings, and get brick count plus mortar volume.

Quick answer

With the default inputs: Wall length 10 · Wall height 3 · Wall thickness 24 cm wall etc.Bricks required (incl. waste) 3,428 blocks

Edit the inputs below to recalculate.
Length LHeight HThickness T
Wall length and height are measured net of openings; thickness sets the brick count per square metre.

Inputs

m²
Sum the area of all doors and windows
%
Cutting and breakage, typically 2-5%

Result

Bricks required (incl. waste)
3,428blocks
Wall area26.00m²
Bricks per m²128blocks
Net bricks3,328blocks
With waste3,428blocks
Masonry volume6.24m³
Mortar volume1.62m³
Cement (32.5)373kg
Sand1.65m³

Standard bricks 240×115×53 mm with 10 mm joints; mortar assumed to be M7.5 cement mortar.

Formula

Bricks per m²N = 64 × number of wythes
Wythes115 mm wall = 1, 240 mm = 2, 365 mm = 3, 490 mm = 4
Wall areaA = length × height − openings
Total bricksN_total = A × N × (1 + waste %)
MortarV = A × thickness × 0.26
10 m × 3 m wall, 240 mm thick, 4 m² of openings: 26 m² of masonry, 128 bricks/m² → 3,328 net, 3,428 with 3% waste, about 1.62 m³ of mortar.

Bricks and mortar per square metre by wall thickness

ThicknessWythesBricks per m²Mortar per m² (m³)Typical use
115 mm wall1640.030Partitions, balcony upstands
240 mm wall21280.062Load-bearing walls, most common
365 mm wall31920.095Insulated external walls, fire walls
490 mm wall42560.127Heavy load-bearing, heritage work

How to work it out

  1. Fix the unit: standard brick 240×115×53, or the actual dimensions of perforated, hollow or AAC block.
  2. Fix wall thickness and bonding: 120 / 180 / 240 / 370 / 490 mm, which sets the count per cubic metre (529 in a 240 mm wall, 552 in a 120 mm wall).
  3. Take the net wall volume: length × height × thickness, less openings, tie columns, ring beams and lintels.
  4. Multiply by the count per cubic metre, then by one plus waste.
  5. Compute mortar separately from the net quantity per cubic metre — never use one-minus-brick-volume directly as consumption.

Where it goes wrong

Material and cost

Fired clay bricks run about 0.40-0.60 each with strong regional and haulage variation; AAC block is roughly 220-320 per m³. Laying labour is typically 180-280 per m³ of wall. Breakage is usually carried at 1-2%, rising to 3% on high-rise jobs with double handling.

On site

Basis

FAQ

Where does 64 bricks per m² come from?
A standard brick is 240×115×53 mm with a 10 mm joint. Each brick occupies (240+10)×(53+10) = 250×63 mm on the wall face, so 1,000,000 ÷ 15,750 = 63.5, rounded to 64. That is one wythe; a 240 mm wall has two, giving 128.
What about perforated bricks or AAC blocks?
Recalculate with the actual unit size: bricks per m² = 1,000,000 ÷ [(length+joint) × (height+joint)]. AAC blocks are commonly 600×200×200 mm, giving about 8.3 units per m² for a 200 mm wall, with much less mortar because thin-bed adhesive is only 3-5 mm.
Should openings, tie columns and ring beams be deducted?
Openings yes. Tie columns, ring beams and lintels also occupy volume and should be deducted, otherwise you over-order. Typical rules ignore openings of 0.3 m² or less. This tool deducts openings only, so subtract structural concrete separately if needed.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Brick Wall Calculator. 2026-10-25. https://jianzhujisuan.com/en/brick-count

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.