算BuildCalc Get a quote

Brick Wall Calculator

Pick a wall thickness, enter length and height, deduct openings, and get brick count plus mortar volume.

Also known as brick quantity · bricks per m2 · brick estimator

Quick answer

With the default inputs: Wall length 10 m · Wall height 3 m · Wall thickness 24 cm wall etc.Bricks required (incl. waste) 3,428 blocksThat is 128 bricks per m² (240 mm wall, 10 mm joints)

Use your own dimensions ↓
Length LHeight HThickness T
Wall length and height are measured net of openings; thickness sets the brick count per square metre.

Inputs

m²
Sum the area of all doors and windows
%
Cutting and breakage, typically 2-5%

Result

Bricks required (incl. waste)
3,428blocks
Wall area26.00m²
Bricks per m²128blocks
Net bricks3,328blocks
With waste3,428blocks
Masonry volume6.24m³
Mortar volume1.62m³
Cement (32.5)373kg
Sand1.65m³
How this is worked out

Standard bricks 240×115×53 mm with 10 mm joints; mortar assumed to be M7.5 cement mortar.

Next up: Brick Veneer Calculator · Mortar Calculator

Formula

Bricks per m²N = 64 × number of wythes
Wythes115 mm wall = 1, 240 mm = 2, 365 mm = 3, 490 mm = 4
Wall areaA = length × height − openings
Total bricksN_total = A × N × (1 + waste %)
MortarV = A × thickness × 0.26
10 m × 3 m wall, 240 mm thick, 4 m² of openings: 26 m² of masonry, 128 bricks/m² → 3,328 net, 3,428 with 3% waste, about 1.62 m³ of mortar.

Bricks and mortar per square metre by wall thickness

ThicknessWythesBricks per m²Mortar per m² (m³)Typical use
115 mm wall1640.030Partitions, balcony upstands
240 mm wall21280.062Load-bearing walls, most common
365 mm wall31920.095Insulated external walls, fire walls
490 mm wall42560.127Heavy load-bearing, heritage work

How to work it out

  1. Fix the unit: standard brick 240×115×53, or the actual dimensions of perforated, hollow or AAC block.
  2. Fix wall thickness and bonding: 120 / 180 / 240 / 370 / 490 mm, which sets the count per cubic metre (529 in a 240 mm wall, 552 in a 120 mm wall).
  3. Take the net wall volume: length × height × thickness, less openings, tie columns, ring beams and lintels.
  4. Multiply by the count per cubic metre, then by one plus waste.
  5. Compute mortar separately from the net quantity per cubic metre — never use one-minus-brick-volume directly as consumption.

Where it goes wrong

Material and cost

Fired clay bricks run about 0.40-0.60 each with strong regional and haulage variation; AAC block is roughly 220-320 per m³. Laying labour is typically CNY 180-280 per m³ of wall. Breakage is usually carried at 1-2%, rising to 3% on high-rise jobs with double handling.

On site

Basis

FAQ

Where does 64 bricks per m² come from?
A standard brick is 240×115×53 mm with a 10 mm joint. Each brick occupies (240+10)×(53+10) = 250×63 mm on the wall face, so 1,000,000 ÷ 15,750 = 63.5, rounded to 64. That is one wythe; a 240 mm wall has two, giving 128.
What about perforated bricks or AAC blocks?
Recalculate with the actual unit size: bricks per m² = 1,000,000 ÷ [(length+joint) × (height+joint)]. AAC blocks are commonly 600×200×200 mm, giving about 8.3 units per m² for a 200 mm wall, with much less mortar because thin-bed adhesive is only 3-5 mm.
Should openings, tie columns and ring beams be deducted?
Openings yes. Tie columns, ring beams and lintels also occupy volume and should be deducted, otherwise you over-order. Typical rules ignore openings of 0.3 m² or less. This tool deducts openings only, so subtract structural concrete separately if needed. The basis is GB 50854-2013, Appendix D, block walls (010402001): volume is measured from the design dimensions and deducts openings, passage holes and voids, plus the volume of reinforced concrete columns, beams, ring beams, cantilever beams and lintels embedded in the wall, and of niches, pipe chases, radiator recesses and hydrant cabinets recessed into it. Beam ends, slab ends, timber blocks and openings of 0.3 m² or less are not deducted. Secondary structure is typically 5-10% of wall volume, so skipping it over-orders bricks and mortar by roughly a tenth. As for 'it is already inside the masonry rate': the work content GB 50854 lists for block walls has only four items - mortar mixing and transport, laying blocks, pointing, and material transport - with no concrete placing, no formwork and no reinforcement. Tie column concrete, formwork and rebar are a separate item under Appendix E, concrete and reinforced concrete works. So 'secondary structure is included in the masonry rate' is a condition a client writes into the contract or a tender clarification (Sichuan clarifications have said exactly that); it is a contractual basis, not the measurement standard. Read the item description and work content before pricing: where the standard says it is measured separately, a contract that folds it in is a concession, not a requirement.

What to calculate next

These jobs are done back to back on site — follow the steps to work through the whole sequence.

Everything for one masonry wallStep 1 of 5

  1. 1Brick Wall Calculator
  2. 2Mortar Calculator
  3. 3Masonry Mortar Mix Calculator
  4. 4Tie Column Quantity Calculator
  5. 5Ring Beam Calculator

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Brick Wall Calculator. 2026-10-25. https://jianzhujisuan.com/en/brick-count

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.