Column Confinement Zone Calculator
Confinement length, hoop spacing and bar size for each detailing class.
With the default inputs: Column long side 500 · Clear height between beams 3600 · Detailing class Class 2 etc.Column end confinement length 600 mm
Edit the inputs below to recalculate.Inputs
Result
| Section long side hc | 500mm |
| Clear height Hn | 3600mm |
| Hn / 6 | 600mm |
| Minimum | 500mm |
| Largest of three | 600mm |
| Governed by | Governed by Hn/6 |
| Max hoop spacing | 100mm |
| Min hoop diameter | 8mm |
| Ground storey base | 1200mm |
| Each side of rigid floor | 500mm |
| Both ends, excl. joints | 1200mm |
| Unconfined length | 2400mm |
Based on GB 50011-2010 (2016 edition) clause 6.3.9 and Table 6.3.7-1. Full-height confinement is required for columns with shear span ratio ≤ 2, clear height to section depth ≤ 4, transfer columns and corner columns of class 1 and 2 frames. The base of the ground storey needs ≥ Hn/3. Hoop leg spacing limits are 200 mm for class 1, 250 mm (or 20 db, whichever is larger) for classes 2-3 and 300 mm for class 4. Where longitudinal reinforcement exceeds 3%, hoops shall be at least 8 mm, spaced within the lesser of 6d and 100 mm, and closed by welding.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| End zone length | l = max(long side hc, Hn/6, 500 mm) |
| Ground storey base | not less than Hn/3 |
| Rigid floor | 500 mm above and below |
| Max spacing | C1 min(6d,100); C2 min(8d,100); C3-4 min(8d,150) |
| Min diameter | C1 10 mm; C2-3 8 mm; C4 6 mm |
| Full height | corner, transfer, low shear span, Hn/hc ≤ 4 |
How to work it out
- Compute the confinement length as the largest of the column's long side, net height ÷ 6, and 500 mm. For a 500 mm column at 3.6 m net height, Hn/6 is 600 mm, so 600 governs.
- Treat the base of ground-floor columns separately: confinement extends at least Hn/3, longer than the general-storey rule, because the column base is where plastic hinges form first.
- Confine 500 mm above and below rigid ground slabs as well — a provision routinely missed in industrial buildings with hardstanding.
- Set the maximum link spacing: class 1 min(6d, 100 mm); class 2 min(8d, 100 mm); classes 3 and 4 min(8d, 150 mm), where d is the main bar diameter.
- Set the minimum link diameter: 10 mm for class 1, 8 mm for classes 2 and 3, 6 mm for class 4.
- Decide whether full-height confinement applies: corner columns, transfer columns, columns with a shear span ratio of 2 or less, and columns whose net height is no more than four times the long side all require it.
Where it goes wrong
- Using 500 mm as the confinement length. The rule takes the largest of three values, and 500 mm is only the floor. For a 500 mm column at 3.6 m the correct figure is 600 mm; building 500 mm loses a link spacing exactly where it matters.
- Treating the ground-floor base as an ordinary storey. The base requires at least Hn/3, far longer than the general rule; omitting it produces the shear failure at the column base that characterises collapse.
- Applying 100 mm spacing universally. Class 1 is min(6d, 100) — at d = 20 mm that is 100 mm, but at d = 12 mm it is 72 mm, tighter than 100.
- Overlooking the special columns needing full-height confinement. Corner columns take biaxial seismic action, transfer columns carry concentrated transfer-beam loads, and low shear-span columns fail in brittle shear.
- Using 90° hooks or open links in confinement zones. Confinement requires closed links with 135° hooks and a straight tail of at least 10d; an open link confines nothing.
Material and cost
Full-height confinement uses 30-50% more link steel than end confinement alone. A 500×500 column at 3.6 m storey takes about 40 kg of links with end confinement and about 70 kg full height. If only a few columns are involved the extra is small, but misclassifying ordinary columns as full-height adds 3-5% to project-wide reinforcement.
On site
- Confinement is measured from the column end at beam or slab soffit, not from floor level. With a 600 mm deep beam the zone extends below the beam, and drawings are easily misread here.
- Link leg spacing also has limits: preferably no more than 200 mm for class 1 and 250 mm for classes 2 to 4. Correct spacing with too few legs still fails.
- Beam-column joint cores must be confined to the same requirement. This is the hardest area to build and is frequently under-provided.
- Net height Hn is measured from the underside of the beam above to the top of the beam below, not storey height. Using storey height shortens the confinement zone.
Basis
- GB 50011-2010 (2016 edition) Code for seismic design of buildings, column confinement zones and link detailing
- GB 50011-2010 (2016 edition) Code for seismic design of buildings, axial load ratio limits for columns
- GB 50666-2011 Code for construction of concrete structures, reinforcement works
FAQ
Why confine the ends and not the middle?
Why take the largest of three instead of just Hn/6?
Where do the 100 mm and 6d limits come from?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Column Confinement Zone Calculator. 2026-10-25. https://jianzhujisuan.com/en/column-hoop-zone