Concrete Curing and Maturity Calculator
Turn curing temperature into maturity and equivalent age, and check the code minimum.
With the default inputs: Mean curing temperature 20 ℃ · Days cured 7 d · Cement type Ordinary Portland etc.Equivalent age at 20°C 7.0 d
Edit the inputs below to recalculate.Inputs
Result
| Maturity | 5040℃·h |
| Estimated strength | 65% |
| Minimum curing | 7d |
| Days still required | 0.0d |
| To 28-day equivalent | 21.0d |
| Temperature factor | 1.00 |
The strength percentage is an empirical curve for ordinary Portland cement and is indicative only. Striking, tensioning and loading must follow site-cured specimens or in-situ testing.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Maturity | M = Σ (T + 10) × Δt (T in °C, Δt in hours) |
| Equivalent age | te = t × (T + 10) ÷ 30 |
| Temperature factor | k = (T + 10) ÷ 30 |
| Minimum curing | 7 days OPC, 14 days slag, 14 days watertight |
How to work it out
- Record the measured concrete temperature (surface or core), not the weather forecast.
- Compute the equivalent age te = actual days × (T + 10) ÷ 30, converting any temperature to days at 20 °C.
- Or compute maturity M = Σ(T + 10) × Δt (T in °C, Δt in hours); 600 °C·h is roughly 60% of the 28-day strength at 20 °C.
- Set the minimum curing period by cement type: 7 days for ordinary Portland, 14 for slag or pozzolanic, 14 with retarders or where impermeability is required.
- Judge striking separately: side forms at ≥1.2 MPa on field-cured specimens (no arris damage), soffits by the strength percentage for the span.
Where it goes wrong
- Using air temperature — 10 °C at noon in winter can mean 2 °C at the concrete surface, halving the equivalent age.
- Assuming enough watering days is enough — curing is temperature × time; below 5 °C even 14 days of watering falls short and insulation is what is needed.
- Using a daily mean and ignoring night lows — 25 °C by day and 5 °C by night averages 15, but hydration is not linear and the cold hours are over-credited.
Material and cost
Covers run 1-2 per m² for polythene and 3-5 for geotextile, usually used together. Winter work needs heating (enclosures, heating blankets, thermal blankets) at 3-5 times the normal cost, and that belongs in the winter premium.
On site
- Impermeable concrete must be cured for at least 14 days — mandatory, not advisory.
- Mass concrete needs the core-to-surface differential held to 25 °C or less through insulation, not by watering it cool.
- Keep measured temperatures in the curing record; it is the only evidence for acceptance and for settling winter premiums.
Basis
- GB 50666-2011 Code for construction of concrete structures, Section 8.5 (curing)
- GB 50204-2015 Code for acceptance of concrete structures, Section 7.4
- GB 50496-2018 Standard for construction of mass concrete (differential limits and monitoring)
FAQ
Why does winter curing take longer?
Is 7 days of curing enough?
When can formwork be struck?