Concrete Pour Sequencing Calculator

Divide a slab into strips and get the volume, truck count and duration for each pour.

Quick answer

With the default inputs: Length 20 · Width 12 · Thickness 0.12 etc.Total volume 28.80 m³

Edit the inputs below to recalculate.
Length LDepth HWidth W
Segment length must be short enough to finish within the initial set. Too long and you get a cold joint — no number of extra trucks will fix it.

Inputs

Usually 2-4 m, the width that can be poured continuously
m³
m³/h

Result

Total volume
28.80m³
Area240.0m²
Pour strips4strips
Volume per strip7.20m³
Trucks per strip1loads
Duration per strip14min
Total duration0.96h
Trucks per hour3.33loads/h
Total trucks4loads

Each strip must be placed before the previous one sets — typically 4-6 hours with ordinary concrete, less in hot weather. Leave and prepare construction joints between strips as the code requires.

Formula

Total volumeV = length × width × thickness
Stripsn = ceil(width ÷ strip width)
Volume per stripV_strip = V ÷ n
Trucks per stripN = ceil(V_strip ÷ truck capacity)
Duration per stript = V_strip ÷ rate × 60
A 20 m × 12 m × 0.12 m slab poured in 3 m strips with 9 m³ trucks at 30 m³/h: 28.80 m³ total, 4 strips of 7.20 m³ each — one truck and about 14 minutes per strip, 0.96 hours in total.

How to work it out

  1. Set the direction first: cut across the short side so the cold joint is as short as possible.
  2. Pours n = ⌈total width ÷ width per pour⌉. The last pour is usually narrower than a standard one, so do not divide equally.
  3. Volume per pour = pour width × element length × thickness, using the actual remaining width for the last one.
  4. Time per pour = volume ÷ actual output. Actual output is the pump's rated figure × 0.5-0.65, not the nameplate.
  5. Trucks per pour = ⌈volume ÷ truck capacity⌉, then check that the truck cycle can keep up with the placing rate.

Where it goes wrong

Material and cost

Placing plans carry no direct cost but decide pump hire (8,000-12,000 per day for a boom pump), truck numbers and night-work premiums. Too few pours means cold-joint repairs; too many means the pump spends its shift repositioning and re-piping.

On site

Basis

FAQ

Why split a pour at all?
Because supply runs out before the area does. If the placed area is larger than the trucks and pump can keep up with, the first concrete sets before the rest arrives and you get a cold joint with reduced strength and watertightness. Strip width should be derived from the volume that can be placed continuously.
What is the difference between a cold joint and a construction joint?
A construction joint is planned, placed where stresses are low, and prepared by scabbling, cleaning and wetting before the next pour. A cold joint forms unintentionally when supply stops; its position is arbitrary — often where stresses are highest — and it counts as a defect needing remedial design.
What truck capacity should I enter?
Common drum sizes are 6, 9 and 12 m³. Actual loads run 0.5-1 m³ below nominal and the last truck is rarely full, so rounding up on nominal capacity usually suffices. For large pours with long hauls, compute on 90% of nominal to avoid running dry mid-strip.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.