Concrete Pour Sequencing Calculator
Divide a slab into strips and get the volume, truck count and duration for each pour.
With the default inputs: Length 20 · Width 12 · Thickness 0.12 etc.Total volume 28.80 m³
Edit the inputs below to recalculate.Inputs
Result
| Area | 240.0m² |
| Pour strips | 4strips |
| Volume per strip | 7.20m³ |
| Trucks per strip | 1loads |
| Duration per strip | 14min |
| Total duration | 0.96h |
| Trucks per hour | 3.33loads/h |
| Total trucks | 4loads |
Each strip must be placed before the previous one sets — typically 4-6 hours with ordinary concrete, less in hot weather. Leave and prepare construction joints between strips as the code requires.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Total volume | V = length × width × thickness |
| Strips | n = ceil(width ÷ strip width) |
| Volume per strip | V_strip = V ÷ n |
| Trucks per strip | N = ceil(V_strip ÷ truck capacity) |
| Duration per strip | t = V_strip ÷ rate × 60 |
How to work it out
- Set the direction first: cut across the short side so the cold joint is as short as possible.
- Pours n = ⌈total width ÷ width per pour⌉. The last pour is usually narrower than a standard one, so do not divide equally.
- Volume per pour = pour width × element length × thickness, using the actual remaining width for the last one.
- Time per pour = volume ÷ actual output. Actual output is the pump's rated figure × 0.5-0.65, not the nameplate.
- Trucks per pour = ⌈volume ÷ truck capacity⌉, then check that the truck cycle can keep up with the placing rate.
Where it goes wrong
- Scheduling on the pump's rated output — 60 m³/h on the plate often means 35 m³/h in practice, so every pour overruns and cold joints follow.
- Dividing the total width equally — 20 m split at 3 m gives seven pours with a 2 m last one, not seven equal 2.86 m pours; truck counts and durations are all wrong.
- Checking only whether one pour can be finished, not whether the next lift can cover it before initial set — most pour-planning failures are cold joints, not incomplete pours.
Material and cost
Placing plans carry no direct cost but decide pump hire (8,000-12,000 per day for a boom pump), truck numbers and night-work premiums. Too few pours means cold-joint repairs; too many means the pump spends its shift repositioning and re-piping.
On site
- Keep each pour inside the initial set: 3-4 h at normal temperature, only about 2 h above 30 °C.
- Leave a 10-15 minute buffer between pours when ordering — better to let the pump idle than to wait for concrete.
- Measure the boom's real reach before fixing the plan, or you will discover the far corner needs re-piping mid-pour.
Basis
- GB 50666-2011 Code for construction of concrete structures, Section 8.3 (construction joints and post-cast strips)
- GB 50204-2015 Code for acceptance of concrete structures, Section 7.4 (joint treatment)
- GB 50164-2011 Standard for quality control of concrete (initial set and transport limits)
FAQ
Why split a pour at all?
What is the difference between a cold joint and a construction joint?
What truck capacity should I enter?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Concrete Pour Sequencing Calculator. 2026-10-25. https://jianzhujisuan.com/en/concrete-pour-plan