Concrete Slab Calculator (Yards & Bags)
Feet and inches straight to cubic yards and bag counts.
Also known as concrete yards · slab concrete calculator · yardage calculator
With the default inputs: Length 10 ft · Width 10 ft · Thickness 4 in etc.Concrete required 1.36 yd³
Use your own dimensions ↓Inputs
Result
| Net volume | 33.3ft³ |
| Volume with waste | 36.7ft³ |
| Cubic yards | 1.36yd³ |
| Truckloads at 9 yd³ | 0.15loads |
| 80 lb bags | 62bags |
| Total weight | 5317lb |
| Short tons | 2.66ton |
How this is worked out
Volume is length x width x thickness, with thickness divided by 12 to become feet. One cubic yard is 27 cubic feet, and concrete weighs about 145 lb per cubic foot. Bag counts use the manufacturer yield (0.60 ft³ for an 80 lb bag, 0.45 ft³ for a 60 lb bag) and are rounded up to whole bags after waste. Above roughly 3 cubic yards (about 130 bags of 80 lb) mixing by hand stops making sense - it will not be consistent and will not keep up with the set, so order a truck instead.
Next up: Concrete Volume Calculator · Concrete Mix Design Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Volume (ft³) = L × W × T(in)/12 | convert inches to feet first |
| Cubic yards = ft³ ÷ 27 | 1 yd³ = 27 ft³ |
| Bags = volume with waste ÷ bag yield | 80 lb = 0.60 ft³, 60 lb = 0.45 ft³ |
| Weight = volume × 145 lb/ft³ | typical concrete unit weight |
How to work it out
- Convert thickness from inches to feet first: 4 in is 0.333 ft, which is the divide by 12 step.
- Volume = length x width x thickness with everything in feet, giving cubic feet.
- Divide by 27 for cubic yards, the unit concrete is ordered and priced in.
- Add waste: 5% flat work, 10% where forms gap or you need fall, 15-20% for footings and trenches.
- Divide by bag yield for bag counts: an 80 lb bag is about 0.60 ft³ and a 60 lb bag 0.45 ft³, rounded up to whole bags.
Where it goes wrong
- Multiplying by thickness in inches - 10 x 10 x 4 gives 400 when the true volume is 33.3 ft³, a 12x error.
- Quoting cubic feet to the plant as cubic yards - a 27x error that turns one truck into 27.
- Ordering the exact net volume with no waste - a short load means a cold joint you have to break out.
Material and cost
Ready-mix in North America runs roughly 130-180 per cubic yard for 3500-4000 psi, including short haul, and varies widely by region with winter and peak season higher. Orders under a full truck (typically 9 yd³) attract a short-load fee of about 70-150, and waiting time starts after 90 minutes on site. Bagged 80 lb 3500 psi mix is about USD 5-8 per bag, which is 220-400 per cubic yard - so above 3 yards order a truck, and keep bags for patching.
On site
- Order at net volume x 1.05 rather than 1.10; returning surplus costs a dumping fee.
- Ask whether pumping is extra - a pump truck commonly starts around 400-800, which rarely pays on small pours.
- Confirm the delivery window the day before; the clock starts while the truck waits on site.
Basis
- ACI 332 Residential Code Requirements for Structural Concrete (slab thickness and reinforcement)
- ACI 318 Building Code Requirements for Structural Concrete
- ASTM C94 Standard Specification for Ready-Mixed Concrete (delivery, slump and volume measurement)
FAQ
How much concrete do I need per square foot at 4 inches?
Should I mix my own or order a truck?
How much waste should I allow?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Concrete Slab Calculator (Yards & Bags). 2026-10-25. https://jianzhujisuan.com/en/concrete-slab-yards