Mass Concrete Temperature Calculator

Placement temperature, adiabatic rise and peak temperature in one step.

Quick answer

With the default inputs: Cement 300 kg/m³ · Cement temp 40 ℃ · Sand 700 kg/m³ etc.Expected peak core temperature 61.6 ℃

Edit the inputs below to recalculate.

Inputs

kg/m³
℃
kg/m³
℃
kg/m³
℃
kg/m³
℃
kJ/kg

Result

Expected peak core temperature
61.6℃
Placement temperature T029.2℃
Adiabatic rise Th43.2℃
Dissipation factor k0.75
Actual rise32.4℃
Surface temperature target36.6℃
Core-surface differential limit≤25℃

Placement temperature is the weighted mean of ingredient temperatures (mixing heat ignored); adiabatic rise uses Th = mce·Q/(c·ρ) with c = 0.97 kJ/(kg·K) and ρ = 2400 kg/m³. The dissipation factor is empirical - thicker pours retain more heat. The 25 ℃ core-surface limit follows GB 50496, with cooling rate usually kept under 2 ℃/day. A real thermal control plan (sensor layout, curing, cooling water) must be prepared separately.Peak above 60 ℃ - use fly ash or slag to cut cement, shade and wet the aggregate, ice the mixing water, and consider embedded cooling pipes.

Formula

T0 = Σ(mi·ti) / Σmiweighted by mass
Th = mce·Q / (c·ρ)c = 0.97, ρ = 2400
Tmax = T0 + Th·kk = 0.60 / 0.75 / 0.85 by thickness
surface ≥ Tmax − 25 ℃differential control
Cement 300 kg at 40 ℃, sand 700 at 30 ℃, gravel 1150 at 28 ℃, water 170 at 15 ℃: placement temperature 29.2 ℃; with Q = 335 kJ/kg the adiabatic rise is 43.2 ℃; at 1-2 m thickness k = 0.75 gives 32.4 ℃ of real rise and a 61.6 ℃ peak, so the surface must stay above 36.6 ℃.

How to work it out

  1. Compute placing temperature: weight × temperature for cement, sand, stone and water, summed and divided by the total heat capacity. Ice or chilled water is the most effective lever.
  2. Compute adiabatic rise: Tmax = W·Q ÷ (c·ρ) × k, with W the cement content, Q the 7-day heat of hydration, c = 0.97 kJ/(kg·°C) and ρ = 2,400 kg/m³.
  3. k depends on pour thickness: 0.60 below 1.5 m, 0.75 for 1.5-3 m, 0.85 above 3 m — thicker sections shed heat more slowly and approach adiabatic.
  4. Peak temperature = placing temperature + adiabatic rise × k.
  5. The governing limits are core-to-surface ≤25 °C and surface-to-air ≤20 °C. Exceeding them means more insulation or casting in layers.

Where it goes wrong

Material and cost

Monitoring (logger plus thermocouples) 10,000-20,000 per project; insulation 10-20 per m²; ice batching adds 15-30 per m³; embedded cooling pipes 40-60 per m. Remediating thermal cracking, by contrast, runs to six figures and is rarely complete.

On site

Basis

FAQ

Does cement temperature really matter that much?
Yes. Bulk cement straight from a tanker can be 70-80 ℃ in summer while aggregate sits near 30 ℃. Cement is only about 13% of the mass but 50 ℃ hotter, contributing 6-7 ℃ to placement temperature - the easiest item to overlook. Dropping cement from 75 to 45 ℃ cuts placement temperature by about 4 ℃, far more effective than wetting aggregate.
What is the difference between adiabatic and actual rise?
Adiabatic rise assumes no heat loss at all - an upper bound. Real elements lose heat to air and ground, so a factor below 1 applies. Thin sections dissipate far more: a 1 m wall may reach only 60% of the adiabatic value, while a 3 m raft exceeds 85% and behaves almost adiabatically. That is why mass concrete is defined by minimum dimension over 1 m, not by volume.
Why the 25 ℃ core-surface limit?
Differential temperature creates thermal stress: the core expands while the surface is held back, putting the surface in tension when its tensile strength is still low. A 25 ℃ differential corresponds to roughly 1 MPa of surface tension, close to early-age capacity. Beyond that, surface cracks form and later become paths for water and chloride. The point is not cooling, it is narrowing the differential.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Mass Concrete Temperature Calculator. 2026-10-25. https://jianzhujisuan.com/en/concrete-temp-control

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.