算BuildCalc

Concrete Yield Calculator

Convert batch weights and density into actual yield and per-m³ contents.

Quick answer

With the default inputs: Cement 3600 · Sand 7000 · Gravel 11500 etc.Actual yield 9.96 m³

Edit the inputs below to recalculate.
Cement1Sand1.84Gravel3Water0.53Per 1 m³ of concrete (schematic)
Figures below the bars are kilograms per cubic metre divided by cement content. Yield is total mass ÷ bulk density, not a simple sum.

Inputs

kg/m³
2350-2450 for plain concrete, about 2500 for reinforced

Result

Actual yield
9.96m³
Total batch weight23900kg
Cement per m³362kg/m³
Sand per m³703kg/m³
Gravel per m³1155kg/m³
Water per m³181kg/m³
Sand ratio37.8%
Water-cement ratio0.500
Binder per m³362kg/m³

Density must be measured (bucket method) because it varies widely with aggregate. If per-m³ contents differ from the batch ticket by more than 2%, check the weighing equipment.

Formula

Batch weightM = cement + sand + gravel + water
YieldV = M ÷ density
Per m³mi = weight ÷ V
Sand ratioβs = sand ÷ (sand + gravel) × 100%
3600 + 7000 + 11500 + 1800 = 23900 kg at 2400 kg/m³ yields 9.96 m³, giving 361 kg cement, 703 kg sand, 1155 kg gravel and 181 kg water per m³ at a 37.8% sand ratio.

How to work it out

  1. Add the batch weights: cement + sand + stone + water + supplementary cementitious materials + liquid admixture. SCMs and admixture are the items most often omitted.
  2. Divide by the measured bulk density, not the nominal 2,400 — measure it, and expect 2,350-2,450.
  3. Compare the resulting yield with the plant's stated volume; a deviation over 2% means the mix was not batched as designed.
  4. Work out the per-cubic-metre consumption of each material (item weight ÷ actual yield) and compare with the design mix.
  5. Sand ratio = sand ÷ (sand + stone) × 100%; a large deviation directly affects workability.

Where it goes wrong

Material and cost

Shortfall is a silent loss: 0.3 m³ missing from a 9 m³ truck is about 150 at C30, and 3% on a 5,000 m³ project is 70,000-80,000 — roughly a project team's margin.

On site

Basis

FAQ

What is shortfall and how is it detected?
Shortfall means the delivered volume is less than what is invoiced. This calculator is the test: yield should equal batch weight divided by density. A batch that yields 9 m³ but is billed as 10 is 10% short. Cross-check with drum volume, weighbridge conversion and density measurement.
Why measure density instead of assuming it?
The same mix with limestone versus granite aggregate can differ by over 100 kg/m³, and lightweight concrete sits near 1800. Assuming 2400 overstates yield by 25% for lightweight aggregate and understates it for heavy aggregate. One bucket measurement beats any textbook figure.
What if the water-cement ratio comes out high?
Check aggregate moisture first. Sand at 5% moisture holds 350 kg of water in a 7000 kg batch; if that is not deducted from the added water, the true ratio runs more than 0.10 above the ticket and the strength drops a grade. This is the commonest cause of low strength on site, far more common than bad cement.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Concrete Yield Calculator. 2026-10-25. https://jianzhujisuan.com/en/concrete-yield

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.