算BuildCalc

Earthwork Calculator

Enter pit dimensions and slope ratio to get cut volume, backfill and spoil to remove.

Quick answer

With the default inputs: Excavation type Rectangular pit · Bottom length 10 · Bottom width 6 etc.Cut volume 231.4 m³

Edit the inputs below to recalculate.
Bottom width mDepth mSlope ratio
Bottom width includes working space (300-800 mm per side) and depth runs from existing ground to formation. A wrong slope ratio shifts the volume by 30%.

Inputs

For a trench, enter trench length
Include working space; for a trench use bottom width
m³
Footing, blinding and equipment bases left in the pit

Result

Cut volume
231.4m³
MethodPit
Top dimensions12.0 × 8.0 m
Cut (bank)231.4m³
Less structure30.0m³
Backfill (compacted)201.4m³
Bank soil needed (0.90 compaction)223.8m³
Spoil off-site (bank)7.6m³
Spoil (loose)9.9m³
Trucks @15 m³1loads

Slope ratios follow the earthwork code. Final values depend on soil, groundwater and the shoring design.

Formula

Rectangular pit (prismoid)V = H/6 × [ab + (a+2mH)(b+2mH) + 4(a+mH)(b+mH)]
TrenchV = (B + mH) × H × L
BackfillV_back = V_cut − structure volume
Loose volumeV_loose = V_spoil × 1.3
A 10×6 m pit 3 m deep with 1:0.33 batter and a 30 m³ structure: 231.4 m³ cut, 201.4 m³ of backfill once compacted, needing 223.8 m³ of bank soil — 7.6 m³ of spoil, 9.9 m³ loose, one 15 m³ truck load.

How to work it out

  1. Fix the base dimensions, then add working space: 300-500 mm each side for concrete footings, 500-800 mm where formwork or brickwork needs access, more again for waterproofing.
  2. Set the batter. Class 1-2 soils use 1:0.33, class 3 1:0.5, class 4 1:0.75. Beyond 5 m depth, or next to existing structures, battering is not acceptable and shoring is required.
  3. Excavation with four battered sides: V = (a+KH)(b+KH)H + K²H³/3, where a and b include working space.
  4. Backfill = excavation − the volume of structure left buried (footings, blinding, basement). Without that deduction the backfill is overstated.
  5. Disposal = excavation × (1 + bulking factor) − backfill. Bulking is 1.2-1.3 for classes 1-2, since loose soil occupies more than intact ground.

Where it goes wrong

Material and cost

Machine excavation 8-25 CNY/m³ including loading; hand digging 40-80. Disposal 15-40 CNY/m³ including tip fees, rising beyond 10 km. Placing and compacting backfill 15-30 CNY/m³.

On site

Basis

FAQ

How do I choose the slope ratio?
By soil type: 1:0.5 to 1:1 for sand and fill, 1:0.33 to 1:0.5 for silt and ordinary clay, 1:0.33 for stiff clay. Pits deeper than 5 m normally need shoring rather than battering, and any pit with groundwater above the base must be dewatered first.
What is the difference between bank, loose and compacted volume?
Bank volume is undisturbed soil and is the basis for measurement and payment. Loose volume is what it becomes after digging, about 1.25-1.35 times larger, and is what trucks are rated in. Compacted volume is smaller than bank volume, so backfill quantities are multiplied by roughly 1.15. Mixing these up doubles or halves your haulage cost.
Should working space be included?
Yes. Formwork and access need room, typically 300-800 mm on each side: 300 mm for formwork on concrete footings, 800 mm where a waterproof membrane is applied, plus more for drainage trenches. Enter bottom dimensions that already include working space.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Earthwork Calculator. 2026-10-25. https://jianzhujisuan.com/en/earthwork

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.