Excavation Volume Calculator
Sloped pit volume: top, base and mid-section via the prismoidal formula.
With the default inputs: Base length 40 m · Base width 30 m · Excavation depth 6 m etc.Excavation volume 9252 m³
Use your own dimensions ↓Inputs
Result
| Top length × width | 49.0×39.0m |
| Top area | 1911m² |
| Base area | 1200m² |
| Mid-section area | 1535m² |
How this is worked out
A sloped pit uses the prismoidal formula V = H/6·(S1 + 4S0 + S2), with S1 the top area, S2 the base area and S0 the mid-section. The slope ratio is horizontal run per metre of depth: 1:0.75 means 0.75 m out for every 1 m down, so top size = base size + 2×ratio×depth. Softer soil and greater depth need flatter slopes (larger ratio); when a deep pit cannot slope, it needs retention (soldier piles, diaphragm wall, ground anchors). This volume is the in-situ (bank) volume - apply a bulking factor (1.2-1.3) for spoil haulage.
Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Top size | Ltop = Lbase + 2·m·H |
| Prismoidal volume | V = H/6·(S1 + 4S0 + S2) |
| Mid-section | S0 = (Lbase+m·H)(Bbase+m·H) |
What one notch of batter costs (same pit: 30 × 20 m base, 5 m deep)
| Slope ratio m | Top size (m) | Excavation (m³) | Loose (m³, ×1.25) | 20 m³ truck loads | vs vertical cut |
|---|---|---|---|---|---|
| 0.00 | 30.0 × 20.0 | 3000 | 3750 | 188 | +0% |
| 0.33 | 33.3 × 23.3 | 3431 | 4288 | 215 | +14% |
| 0.50 | 35.0 × 25.0 | 3667 | 4583 | 230 | +22% |
| 0.75 | 37.5 × 27.5 | 4031 | 5039 | 252 | +34% |
| 1.00 | 40.0 × 30.0 | 4417 | 5521 | 277 | +47% |
| 1.25 | 42.5 × 32.5 | 4823 | 6029 | 302 | +61% |
Same base, same depth, only the batter changes from 0 to 1.25, and the volume goes from 3000 to 4823 m³ — 61% more soil, 114 more truck loads. That is why the slope ratio is not a place to round up 'for safety': too steep is a safety problem, too flat is a cost problem, and both have to be counted. The loose column uses 1.25; real clay runs 1.2-1.3 and sand 1.1-1.15, so change it by soil type rather than applying 1.25 across the board. Note also that once the top size crosses the site boundary or reaches a neighbouring footing, the scheme changes from open cut to retention — soldier piles, anchors, props — which is a different sum entirely and outside this page's formula.
Basis
- GB 50854-2013 — measurement rules for earthworks (excavation, backfill, disposal)
- GB 50854-2013 — the working face and slope allowances are added to the net dimension
FAQ
How do I choose the slope ratio?
Why apply a bulking factor to the volume?
Should I add a working space before calculating?
Is it always safer to use a flatter slope?
Can the volume be priced straight off?