Movement Joint Width Calculator

Joint width from thermal movement plus allowances.

Quick answer

With the default inputs: Structural length between joints 60 · Temperature range 30 ℃ · Expansion coefficient 1.0 ×10⁻⁵/℃ etc.Minimum joint width 60 mm

Edit the inputs below to recalculate.
Construction and s mm
Width = thermal movement + construction tolerance + allowance, where movement is α × L × ΔT with α = 1.0×10⁻⁵ for concrete.

Inputs

℃
×10⁻⁵/℃

Result

Minimum joint width
60mm
Thermal movement (one way)18.0mm
Two-way movement36.0mm
Allowance20mm
Calculated width56.0mm
Joint spacing reference60m

ΔL = α·ΔT·L with α about 1.0×10⁻⁵ per ℃ for concrete. The width must cover two-way movement - expansion into the joint when hot, contraction when cold - plus construction tolerance, seismic displacement and sealant movement capability; twice the calculated value plus 20-30 mm is customary. Maximum spacing without joints is set in GB 50010 clause 8.1.1 (55 m for cast-in-situ frames, 45 m for shear walls, 40 m for basements, relaxable by calculation). Drawings govern.

Formula

ΔL = α × ΔT × Lα ≈ 1.0×10⁻⁵ per ℃, L in mm
Width = 2×ΔL + allowancestwo-way movement
Round up to 10 mm
60 m structure with a 30 ℃ range: 18.0 mm one way, 36.0 mm two way, plus 20 mm gives 56.0 mm, rounded to 60 mm. A settlement joint still needs checking to 50-120 mm by ground conditions.

How to work it out

  1. Fix the joint spacing L from the code limits: 55 m for cast-in-situ frames indoors, 35 m exposed, 45 m for shear walls.
  2. Compute ΔT as the difference between the temperature at construction and the service extreme. In the north that is winter minimum against placing temperature; in the south it is the summer maximum.
  3. Movement ΔL = α × L × ΔT, with α = 1.0 × 10⁻⁵ per °C for concrete and 1.2 × 10⁻⁵ for steel.
  4. Joint width = ΔL + construction tolerance + seismic allowance. Tolerance is 10-15 mm; the seismic allowance runs 15-50 mm by intensity.
  5. Check the minimum: a movement joint is never less than 100 mm, and seismic joints add roughly 20 mm per 10 m of height.

Where it goes wrong

Material and cost

Complete joint construction with waterstop, cover and filler 150-400 CNY/m. Rubber waterstop 30-80 CNY/m, stainless cover 120-250, bitumen felt fill 15-30.

On site

Basis

FAQ

Why two-way movement?
Both sides move. In heat the two blocks close the gap, in cold they separate; the sealant and waterstop must both compress and stretch, so twice the movement gives travel in both directions. Sizing on one direction only lets the joint open too far in winter, tearing the waterstop - and that is where leaks begin.
Can a construction strip replace a movement joint?
A strip solves construction-period shrinkage and differential settlement, but it gets concreted and closes - after that the structure is continuous again and long-term thermal movement still needs a real joint (or prestressing, sliding layers and similar). It is not a permanent joint.
What is wrong with a wider joint?
The waterstop and sealant must accommodate more movement, raising material and workmanship demand; the floor slab is interrupted, so shear keys or dowels, finishes, waterproofing and fire separation all become harder; and in hospitals or labs a wide gap is harder to keep clean. Joint width is a balance - adequate, not generous.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Movement Joint Width Calculator. 2026-10-25. https://jianzhujisuan.com/en/expansion-joint-width