Footing Concrete Calculator
Length, width and depth to yards and bags.
Also known as footing volume · pad footing concrete · strip footing concrete
With the default inputs: Length 40 ft · Footing width 16 in · Footing depth 8 in etc.Concrete required 1.45 yd³
Use your own dimensions ↓Inputs
Result
| Net volume | 35.6ft³ |
| With waste | 39.1ft³ |
| Yards per linear foot | 0.0329yd³/ft |
| 80 lb bags | 66bags |
| Total weight | 5671lb |
| Short tons | 2.84ton |
How this is worked out
A strip footing is a box: length x width x depth, with width and depth divided by 12 when given in inches. The yards per linear foot line is the useful one - measure the total run and multiply instead of re-entering parameters. Footings overlap at L and T intersections so the true volume is slightly less than shown, but the waste allowance more than covers it. This figure excludes the gravel blinding layer, which is calculated separately - typically 4-6 in thick and 6 in wider than the footing each side.
Next up: Concrete Volume Calculator · Concrete Mix Design Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Volume = L × (W/12) × (D/12) × runs | width and depth inches to feet |
| Cubic yards = volume ÷ 27 | |
| Yards per ft = (W/12 × D/12) ÷ 27 | multiply by total length |
How to work it out
- Measure total footing length off the drawings, taking corners on the centreline without double counting.
- Fix width and depth - 16 x 8 in is typical, 20 x 10-12 in for two storeys.
- Volume = total length x width/12 x depth/12 x number of runs.
- Add 10% waste and convert to cubic yards.
- The gravel blinding is separate: 4-6 in thick and 6 in wider each side, not part of the concrete.
Where it goes wrong
- Entering width and depth in feet - typing 16 for a 16 in footing makes it 144 times too big, the classic imperial error.
- Folding the gravel blinding into the concrete figure - different material, different operation, and it sends the plant the wrong volume.
- Measuring only the wall lengths and missing corners - foundations run continuously through corners, and under-ordering leaves a cold joint.
Material and cost
Concrete for strip footings at 3500 psi including pumping runs about USD 150-220 per cubic yard, with a short-load fee on small pours. Excavation, formwork, steel and placing as a package commonly comes in at 25-60 per linear foot depending on depth and soil. Rock excavation or a deep trench needing shoring doubles that. Formwork and labour usually cost more than the concrete.
On site
- Keep the top of the footing level - shoot it with a laser; more than 1/2 in out and the wall above gets difficult.
- Clear loose spoil from the trench and dampen it before pouring, or the concrete bleeds water into the ground and loses strength at the base.
- Set anchor bolts to the drawing spacing and place them within two hours while the mix is still plastic; after initial set you are drilling and epoxying.
Basis
- ACI 332 Residential Code Requirements for Structural Concrete (footing size and reinforcement)
- IRC International Residential Code, Chapter R403 (footing depth, width and minimum size)
- ACI 318 Building Code Requirements for Structural Concrete
FAQ
How wide and deep should the footing be?
Why is a gravel blinding layer needed?
Do I need to correct for corner overlaps?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Footing Concrete Calculator. 2026-10-25. https://jianzhujisuan.com/en/footing-concrete