Formwork Plywood Calculator
Plywood sheet count from area, sheet size and reuse cycles.
Also known as shuttering plywood · plywood sheets · form ply
With the default inputs: Formwork area 500 m² · Sheet size 1220×2440 mm · Waste 8% etc.Plywood sheets 61 sheets
Use your own dimensions ↓Inputs
Result
| Area per sheet | 2.977m² |
| Area with waste | 540m² |
| After reuse cycles | 180m² |
How this is worked out
Formwork plywood comes in the standard 1220×2440 mm sheet (2.977 m²) and the small 915×1830 size. Take-off = area ×(1+waste) ÷ reuse cycles, rounded up. Waste comes from trimming, odd shapes and damage, usually 5-15%; reuse cycles are how many times one batch is reused - standard plywood 3-6 times, film-faced up to 6-8, architectural (fair-faced) often only 1-2. More reuse lowers per-use cost, but deformed panels degrade the concrete surface.
Next up: Formwork Striking Time Estimator · High Strength Bolt Torque Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Area per sheet | Asheet = W×L (1220×2440 = 2.977 m²) |
| Sheets | N = ⌈area×(1+waste%) ÷ reuse⌉ |
Sheet count by area and reuse cycles (1220×2440, 8% waste, same formula as this page)
| Formwork area (m²) | 1 cycle | 2 cycles | 3 cycles | 5 cycles | Area per sheet (m²) |
|---|---|---|---|---|---|
| 100 | 37 | 19 | 13 | 8 | 2.977 |
| 200 | 73 | 37 | 25 | 15 | 2.977 |
| 500 | 182 | 91 | 61 | 37 | 2.977 |
| 1000 | 363 | 182 | 121 | 73 | 2.977 |
| 2000 | 726 | 363 | 242 | 146 | 2.977 |
| 5000 | 1815 | 908 | 605 | 363 | 2.977 |
Waste allowance by element (typical ranges, not a bill-of-quantities figure — check what your last floor actually used)
| Element | Typical waste | Where the waste comes from |
|---|---|---|
| Regular walls and large slabs | 5-8% | Only edge trimming and corners; most of the sheet is used |
| Beams, columns, many junctions | 10-15% | Lots of short pieces; one sheet will not cover many faces |
| Curved, circular and irregular shapes | 15-25% | Whatever is left after the curve is scrap |
| Second-fix work and small patches | 15-20% | Sheets are bought whole even when a small piece is needed |
| Fair-faced concrete | 10-15% | Joint and tie-hole positions are critical, so offcuts cannot be used up |
Panel type against reuse cycles (typical values, not code limits — reuse depends on curing, release agent and stripping time)
| Panel type | Typical thickness (mm) | Typical reuses | Off-form finish | Best for |
|---|---|---|---|---|
| Plain plywood (poplar core) | 12-15 | 3-4 | Fair, needs sanding | Footings, basements, concealed work |
| Phenolic film-faced | 15-18 | 6-8 | Good, clean release | Shear walls, beams and slabs |
| High-density film-faced (imported face) | 18-21 | 8-12 | Excellent, near fair-faced | Fair-faced concrete, exposed walls |
| Bamboo plywood | 12-15 | 8-10 | Good, wear resistant | Typical floors, heavily reused areas |
| Steel frame with timber face | 18 | 15-20 (face replaced) | Excellent | High-rise typical floors, aluminium formwork substitute |
Basis
- GB 50666-2011, Chapter 4 — formwork design, including the deflection limit of l/400
- GB 50204-2015, Chapter 4 — formwork acceptance before placing concrete
FAQ
How do I set the reuse cycles?
Why use developed area instead of floor area?
How many square metres in a 1220×2440 plywood sheet?
How many sheets for 500 m² of formwork?
Is more reuse always cheaper?
How is formwork area calculated for beams and columns?