Formwork Prop Calculator
Prop count and per-prop load check - see at once if the grid is dense enough.
With the default inputs: Slab length 10 m · Slab width 8 m · Longitudinal spacing 0.9 m etc.Number of props 108 bars
Use your own dimensions ↓Inputs
Result
| Longitudinal rows | 12bars |
| Transverse rows | 9bars |
| Tributary area per prop | 0.74m² |
| Load per prop | 5.2kN |
| Prop capacity | 25kN |
| Utilisation | 21% |
| Check | OK |
How this is worked out
Props form a grid, count = (⌊length ÷ longitudinal⌋ + 1) × (⌊width ÷ transverse⌋ + 1) with a row at each edge. Load per prop = design load × tributary area, checked against capacity. This is the average split; under beams, at edges and near pour strips loads concentrate and need local tightening. The design load already includes concrete, formwork and live load - 6-8 kN/m² for a typical slab. Tall or heavy slabs need a dedicated scheme, not this rough check.
Next up: Formwork Turnover Calculator · Formwork Lateral Pressure Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Prop count | n = (⌊L÷sl⌋+1) × (⌊W÷sw⌋+1) |
| Tributary area | A₁ = area ÷ count |
| Load per prop | N = A₁ × design load |
| Check | N ≤ prop capacity |
How to work it out
- Props = ⌈slab length ÷ longitudinal spacing⌉ × ⌈slab width ÷ transverse spacing⌉; spacing is usually 0.9-1.2 m.
- Loaded area per prop = spacing × spacing; prop load = slab pressure × loaded area.
- Check prop load ≤ allowable capacity; if exceeded, tighten the grid.
- Horizontal ledgers run continuously at each lift with the prescribed storey height and step - never omit them.
- Vertical and horizontal bracing must be provided; this is the crux of overall stability.
Where it goes wrong
- Props too far apart - each one is overloaded, buckles, and the whole falsework collapses; the deadliest form of accident.
- Props on soft ground with inadequate base plates - uneven settlement tilts the frame or overturns it.
- Bracing omitted - the frame fails out-of-plane; a gust of wind or a concrete pour surge brings it down.
Material and cost
Falsework is priced by volume or developed area and rented by tonne·day. The extra material for tighter props and bracing is far less than the compensation and downtime of one collapse - safety margin is not where you save.
On site
- Set base plates or cast on hard ground to avoid uneven settlement.
- Install ledgers and bracing as the frame goes up, not patched in at the end.
- Inspect before pouring and post a watcher during the pour; stop immediately on any creaking or deformation.
Basis
- EN 1065:1998 Adjustable telescopic steel props — Product specifications, design by calculation and testing
- EN 12812:2008 Falsework — Performance requirements and general design
- BS 5975:2019 (falsework design and prop layout)
FAQ
What prop spacing is right?
Why not strike the formwork too early?