算BuildCalc

Formwork Turnover Calculator

Initial formwork area and replacement allowance from total area and cycles.

Quick answer

With the default inputs: Total contact area 1000 m² · Planned cycles 6 cycles · Loss per cycle 5% etc.Initial formwork area 188.7 m²

Edit the inputs below to recalculate.
Length LWidth W
The first-set area is contact area, not floor area. Turnover runs 5-8 cycles before panels need replacing.

Inputs

m²
cycles
Plywood 5-8 cycles, steel forms 30+
%

Result

Initial formwork area
188.7m²
Total contact area1000.0m²
Cycles6cycles
Cumulative factor5.298
Replacement over the run132.5m²
Total area purchased321.2m²
Sheets for first set64sheets
Sheets including replacements108sheets
Area per sheet2.977m²
Sheets per m² incl. replacement0.108sheets/m²

Loss covers edge trimming and breakage only, not waste from poor setting out. Flipping plywood extends life by 2-3 cycles; levering forms off with a crowbar is the main cause of loss, and proper striking tools halve it.

Formula

Cumulative factorS = Σ(1 − r)^(k−1) for k = 1…cycles
Initial areaA = total ÷ S
ReplacementA = initial × (cycles − S)
SheetsN = ceil(initial ÷ sheet area)
1000 m² of contact area over 6 cycles at 5% loss: cumulative factor 5.298, initial area 188.7 m², replacement 132.4 m² — 321.1 m² in total, or 64 sheets at 2440 × 1220.

How to work it out

  1. Establish the total contact area: measure the face in contact with concrete — beams take soffit plus two sides (not deducting slab thickness), slabs take soffit, columns four faces, walls two faces.
  2. Set the number of reuses. Plywood 6-8, bamboo ply 8-10, modular steel 50+, aluminium 200+. The figure depends on material, striking time and care.
  3. Area per set = total area ÷ reuses. That is what must be on site simultaneously — an investment figure, not a total.
  4. Allow replacements: every strike and re-erection damages edges, adds holes and distorts panels. Take 3-8% per cycle; cumulative replacement = set area × rate × cycles.
  5. Round the set area up to whole sheets (2440 × 1220 = 2.98 m²) and add 5% for irregular locations and patching.

Where it goes wrong

Material and cost

15 mm plywood 45-75 CNY per sheet (15-25 CNY/m²), bamboo ply 60-95, modular steel hire 0.8-1.5 CNY/m² per day, aluminium 1000-1500 CNY/m² to buy or 25-40 per m² per cycle to hire.

On site

Basis

FAQ

Why not just divide area by cycles?
Because forms are lost each cycle, so usable area decays rather than stepping down evenly. Plain division underestimates the initial purchase: at 1000 ÷ 6 = 167 m², only 129 m² survives to cycle six, forcing a mid-run purchase that costs more.
Plywood or steel forms?
Plywood is cheap, easy to work and suits irregular shapes, but only lasts 5-8 cycles so its amortised cost can exceed steel; steel lasts 30+ cycles and gives a better finish, but needs a big upfront spend, lifting gear and costly adaptation. Residential standard floors favour aluminium or steel, basements and irregular work favour plywood.
What loss rate is typical?
3-5% on well-run sites, 5-8% generally, and over 10% with poor control or many irregular shapes. Striking method dominates: levering, careless stacking and weather exposure all shorten life sharply. Raising and covering the stack and applying release agent can cut loss by 2-3 points for very little cost.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Formwork Turnover Calculator. 2026-10-25. https://jianzhujisuan.com/en/formwork-turnover

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.