Full Scaffold Material Calculator
Standards, tube length and weight, couplers and board area.
With the default inputs: Length 6 · Width 4 · Height 4 etc.Plan area 24.00 m²
Edit the inputs below to recalculate.Inputs
Result
| Standards | 24bars |
| Standard length | 100.8m |
| Lift levels | 3levels |
| Ledger and transom length | 144.0m |
| Total tube length | 244.8m |
| Tube weight | 940kg |
| Couplers (about 1.5 per m) | 368pcs |
| Board area | 24.0m² |
| Tube per m² | 10.2m/m² |
This is a material take-off, not a scaffold design. Above 8 m, or where the scaffold supports structural concrete, a chartered engineer must prepare and check a design to JGJ 130 covering standard stability, bearing capacity and ties.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Standards | N = (floor(L÷s)+1) × (floor(W÷s)+1) |
| Standard length | L = N × (height + 0.2) |
| Lift levels | n = floor(height ÷ lift) + 1 |
| Ledger length | L = (rows × L + columns × W) × levels |
| Tube weight | W = total length × 3.84 kg/m |
Full scaffold material content (1.2 m standards, 1.5 m lifts)
| Height (m) | Tube (m/m²) | Tube (kg/m²) | Couplers per m² |
|---|---|---|---|
| 3 | 8.2 | 31.5 | 12 |
| 4 | 10.2 | 39.2 | 15 |
| 6 | 16.2 | 62.2 | 24 |
| 8 | 20.2 | 77.6 | 30 |
| 10 | 24.2 | 92.9 | 36 |
How to work it out
- Standards = (length ÷ spacing + 1) × (width ÷ spacing + 1). Both directions get the plus one, because every edge needs a row.
- Total standard length = count × height, allowing for joints — tube comes in 6 m lengths, so anything taller needs splicing with extra lap length.
- Ledger levels = height ÷ lift, rounded up plus one for the base and top rails. Each level takes the sum of both directions.
- Total tube = standards + ledgers + bracing (estimate 15-25% of the elevation area), times 3.84 kg/m for Φ48 × 3.0.
- Couplers: 1.5 right-angle couplers per standard/ledger intersection plus 2 swivel couplers per splice; decking by laid area, normally one full lift.
Where it goes wrong
- Dropping the plus one — a 6 m run at 1.2 m comes out as five standards when six are needed, leaving the edge unsupported and the frame cantilevered.
- Forgetting the base rails — longitudinal and transverse rails within 200 mm of the ground are mandatory; without them the standard bases are unrestrained and stability halves.
- Faking the bracing as a percentage of area — bracing must be laid out to the code (continuous at the perimeter, one line every 6-8 m internally); a percentage estimate leaves gaps and fails inspection.
- Treating a full hall as a support frame without load design — formwork support spacing must come from the load, not from a default 1.2 m; spacing tightens under beams.
Material and cost
Full hall complete (hire plus erection) 25-50 CNY/m³ of enclosed volume, or 30-60 CNY/m² of plan. Tube hire 4-6 CNY/m per month, couplers 0.3-0.5 each per month.
On site
- Size formwork support spacing from beam and slab loads; tighten under beams and give heavy beams their own standards at 600-900 mm.
- Supports over 8 m high, 18 m span or 15 kN/m² load are major hazard installations requiring expert review.
- Splice standards butt-to-butt with joint couplers, never by lapping, and stagger adjacent splices by at least 500 mm.
Basis
- JGJ 130-2011 Technical code for steel tubular scaffold safety, Chapter 6
- JGJ 162-2008 Technical code for safety of building formwork
- GB 50666-2011 Code for construction of concrete structures, Section 4.3
FAQ
How does a full scaffold differ from a facade scaffold?
Why 3.84 kg/m for the tube?
Why is lift height limited?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Full Scaffold Material Calculator. 2026-10-25. https://jianzhujisuan.com/en/full-scaffold