Grout Quantity Calculator
Volume, weight, bags and water in one pass.
With the default inputs: Length 1.2 · Width 0.8 · Grout thickness 50 etc.Dry grout required 110.9 kg
Edit the inputs below to recalculate.Inputs
Result
| Volume incl. over-pour | 0.050m³ |
| Bags (whole) | 5bags |
| Dry grout as ordered | 125.0kg |
| Mixing water | 16.3L |
| Slurry volume weight | 141.3kg |
| Water per bag | 3.25L |
Grout must be mixed to the manufacturer water ratio: 1% extra water can cost 8-10% strength, while too little leaves it unable to flow into voids. Meter water by weight; a marked bucket by volume is only valid if you allow for slurry density. Over-pour factor 1.03-1.10, higher with open faces. Use each batch within 30 minutes, 20 in hot weather.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Volume = L × W × T × over-pour | T in mm, divide by 1000 |
| Dry weight = volume × density | |
| Water = dry weight × water ratio | by weight, 1 kg ≈ 1 L |
| Bags = ceil(dry weight ÷ bag size) |
How to work it out
- Compute the net volume: length × width × grout depth, dividing by 1,000 when the depth is in mm.
- Apply an overfill factor of 1.05-1.10. Equipment grouting has to flow out of the form and secondary grouting must fill anchor holes, none of which the net volume covers.
- Dry weight = net volume × overfill factor × bulk density. Grouts run 2,100-2,300 kg/m³, with about 5% spread between suppliers.
- Bags = ⌈dry weight ÷ bag size⌉, commonly 25 kg.
- Water = dry weight × water ratio, strictly per the manufacturer; typically 12-14%, and extra water costs strength and causes bleeding.
Where it goes wrong
- Ordering on net volume alone — overflow and anchor-hole filling take 5-10%, so ordering net is always short and topping up mid-pour creates layers.
- Adding water for flow — the water ratio is the balance point between strength and flow; 1% more water loses 5-8% strength and the bleed water leaves a porous layer at the base.
- Mixing too much to use slowly — working life is only 20-30 min, after which flow is gone and forcing it in leaves voids.
Material and cost
High-strength non-shrink grout runs 1,200-2,200 per tonne (rising from C40 to C80); plain cementitious grout 600-900. A cubic metre of secondary grouting is about 2,500-5,000 in material.
On site
- Scabble and clean the base, then pre-soak for 24 h with no standing water, or the grout will give up its water and crack.
- Use a high-level hopper or pressure grouting from one side and let the grout flow, rather than pouring from all sides.
- In winter keep water below 30 °C and materials above 5 °C; cold grout can stay unset for hours.
Basis
- GB/T 50448-2015 Technical code for application of cementitious grout (placing and curing)
- JC/T 986-2018 Cementitious grout (performance requirements)
- GB 50205-2020 Code for acceptance of steel structure construction, Chapter 8 (equipment foundations and secondary grouting)
FAQ
Why can't grout be watered like ordinary mortar?
What thickness should the grout layer be?
What about hot weather?