Jet Grouting Calculator
Column volume and cement for jet-grout piles in one go.
With the default inputs: Column diameter 600 mm · Column length 15 m · Number of columns 40 pcs etc.Cement 59.4 t
Use your own dimensions ↓Inputs
Result
| Section area | 0.2827m² |
| Volume per column | 4.24m³ |
| Total volume | 169.6m³ |
| Cement content | 350kg/m³ |
How this is worked out
Jet grouting forms a column by cutting, mixing and replacing soil with a 20-40 MPa cement jet, giving flexible diameter and depth for tight spaces, ground improvement next to existing structures, and cut-off strengthening. Cement = column volume × cement content, usually 300-400 kg/m³ - higher than SMW (15-20% of soil weight, roughly 270-360 kg/m³ and denser), so jet grouting costs more and is used locally. Return spoil carries off some cement, so real usage runs slightly higher.
Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Volume per column | V₁ = πD²/4·L |
| Total volume | V = V₁·n |
| Cement | M = V·content / 1000 (t) |
Quantities per metre by diameter (from this page's formulas, 350 kg/m³ cement)
| Diameter (mm) | Section area (m²) | Volume (m³/m) | Cement (kg/m) | 15 m column (t) |
|---|---|---|---|---|
| 600 | 0.283 | 0.283 | 99 | 1.48 |
| 800 | 0.503 | 0.503 | 176 | 2.64 |
| 1000 | 0.785 | 0.785 | 275 | 4.12 |
| 1200 | 1.131 | 1.131 | 396 | 5.94 |
Single, double and triple fluid: what changes
| Method | Column diameter (mm) | Jet medium | Typical pressure (MPa) | Typical depth (m) | Character |
|---|---|---|---|---|---|
| Single fluid | 400-600 | Cement grout | 20-30 | up to 20 | Simplest; small diameter, uniformity depends on the withdrawal rate |
| Double fluid | 600-800 | Grout + compressed air | 20-30 | up to 25 | The air shroud extends the jet, one size larger |
| Triple fluid | 800-1200 | Water, air and grout separately | water 30-40 | up to 30 | High-pressure water cuts first, grout replaces it: largest diameter, most return flow |
Basis
- JGJ 79-2012 — Technical code for ground treatment of buildings, jet grouting chapter
- JGJ 79-2012 — column diameter and spacing are set by trial columns on site, not by formula
FAQ
What cement content should I use?
Can jet-grout columns form a cut-off wall?
Jet grouting or deep mixing - which one?
Jet grouting or soil mixing?
How do I account for the return flow, and can it eat my margin?
How is the column diameter fixed - can I just take it off the drawing?
Why is jet grouting so much more expensive than soil mixing?