Labour Days and Crew Calculator
Man-days, crew size and labour cost from output rates.
With the default inputs: Quantity 100 · Output per man-day 8 per man-day · Planned duration 10 days etc.Total man-days 12.5 man-days
Edit the inputs below to recalculate.Inputs
Result
| Quantity | 100.00 |
| Output per man-day | 8.00per man-day |
| Crew required (exact) | 1.32persons |
| Crew required (rounded up) | 2persons |
| Duration with that crew | 6.6days |
| Labour cost | 4375CNY |
| Output per man-day | 8.00per man-day |
| Man-days per unit | 0.1250man-days |
Output rates come from local estimating standards or your own records, and vary 30% or more between regions and crews. Dividing by attendance is essential: 100 man-days needed, but ten men at 95% attendance deliver only 95. Rounding the crew up changes the duration, so check the result against the programme.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Man-days | quantity ÷ output per man-day |
| Crew | man-days ÷ (duration × attendance) |
| Rounding | round up to a whole person |
| Actual duration | man-days ÷ (crew × attendance) |
| Cost | man-days × rate |
| Unit labour | man-days ÷ quantity |
How to work it out
- Total labour days = quantity ÷ output norm, where the output norm is how much one labour day produces, say 8 m³ of brickwork.
- Confirm which norm you have: output and time norms are reciprocals. A time norm of 0.125 labour days per m³ is an output of 8 m³ per day, and mixing them is a 64-fold error.
- Labour required = total labour days ÷ (programme duration × attendance rate). Attendance covers sickness and leave, normally 90-95%.
- Labour cost = total labour days × daily rate, banded by general, skilled and specialist.
- Sanity-check the headcount: a work face holds a limited number of people, so a computed 200 on a 50 m² face means the programme is unrealistic and needs more faces or more time.
Where it goes wrong
- Confusing output and time norms — 8 m³ per day against 0.125 days per m³, and getting the direction wrong changes the answer 64-fold.
- Ignoring attendance — 100 on the books is not 100 on site every day, and assuming full attendance loses the programme.
- Ignoring productive days — rain, wind, heat and inspections mean outdoor work typically gets 75-85% of calendar days.
- Sizing the crew without the work face — a masonry face takes 15-20 people at once, so a computed 100 is theoretical.
Material and cost
General labour 200-300 CNY per day, skilled trades 350-500, specialists 500-800. Labour is normally 20-30% of construction cost with materials included.
On site
- Output norms vary by region and contractor; your own historical data beats the published norm, which is only a reference.
- Distinguish day rate from measured rate: measured work is 20-30% more productive but quality varies more.
- Crashing is not linear — doubling the crew typically buys 60% more output because the face is congested and materials lag.
Basis
- GB 50500-2013 Code of bills of quantities and valuation for construction works
- GB/T 50502-2009 Code for design of construction organisation
- National consumption quotas for building and decoration works (MOHURD)
FAQ
Are output and time standards reciprocals?
Why does 1.32 people become a crew of 2?
Is man-days times rate an accurate labour cost?