Labour Days and Crew Calculator

Man-days, crew size and labour cost from output rates.

Quick answer

With the default inputs: Quantity 100 · Output per man-day 8 per man-day · Planned duration 10 days etc.Total man-days 12.5 man-days

Edit the inputs below to recalculate.

Inputs

Same unit as the output rate
per man-day
Quantity one man-day completes
days
%
CNY

Result

Total man-days
12.5man-days
Quantity100.00
Output per man-day8.00per man-day
Crew required (exact)1.32persons
Crew required (rounded up)2persons
Duration with that crew6.6days
Labour cost4375CNY
Output per man-day8.00per man-day
Man-days per unit0.1250man-days

Output rates come from local estimating standards or your own records, and vary 30% or more between regions and crews. Dividing by attendance is essential: 100 man-days needed, but ten men at 95% attendance deliver only 95. Rounding the crew up changes the duration, so check the result against the programme.

Formula

Man-daysquantity ÷ output per man-day
Crewman-days ÷ (duration × attendance)
Roundinground up to a whole person
Actual durationman-days ÷ (crew × attendance)
Costman-days × rate
Unit labourman-days ÷ quantity
100 m² at 8 m² per man-day over 10 days at 95% attendance and 350 per man-day: 12.5 man-days, 1.32 people rounded to 2, an actual 6.6 days and 4375 in labour.

How to work it out

  1. Total labour days = quantity ÷ output norm, where the output norm is how much one labour day produces, say 8 m³ of brickwork.
  2. Confirm which norm you have: output and time norms are reciprocals. A time norm of 0.125 labour days per m³ is an output of 8 m³ per day, and mixing them is a 64-fold error.
  3. Labour required = total labour days ÷ (programme duration × attendance rate). Attendance covers sickness and leave, normally 90-95%.
  4. Labour cost = total labour days × daily rate, banded by general, skilled and specialist.
  5. Sanity-check the headcount: a work face holds a limited number of people, so a computed 200 on a 50 m² face means the programme is unrealistic and needs more faces or more time.

Where it goes wrong

Material and cost

General labour 200-300 CNY per day, skilled trades 350-500, specialists 500-800. Labour is normally 20-30% of construction cost with materials included.

On site

Basis

FAQ

Are output and time standards reciprocals?
Yes. The output rate says how much one man-day completes, in m² per man-day; the time standard says how many man-days a unit needs, in man-days per m². 8 m² per man-day is 0.125 man-days per m². Quotes read better in time standards, crew planning in output rates — take the reciprocal.
Why does 1.32 people become a crew of 2?
Because people do not split. Rounding up cuts the duration to 6.6 days but leaves idle time; one person alone takes 13.2 days and misses the date. In practice you crew one and add help on the critical days, or borrow from an adjacent trade. The decision compares the deadline against the cost of idle time, not the arithmetic.
Is man-days times rate an accurate labour cost?
Only as a baseline. Real settlement works three ways: daywork against attendance, piecework against measured quantity, and supply-and-fix. Piecework rates already carry the efficiency risk and typically run 15-30% above the computed man-day cost. Estimate the floor from standards, quote from piecework rates, and the gap is your margin.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Labour Days and Crew Calculator. 2026-10-25. https://jianzhujisuan.com/en/labor-productivity

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.