Lighting Level and Fixture Calculator

Lumen method fixture count, achieved lux and power density.

Inputs

m²
lx
Office 300, classroom 300, corridor 100, fine work 500
lm
18 W LED about 1800, 36 W about 3600
0.7-0.8 for light small rooms, 0.4-0.5 for dark large ones
0.8 clean, 0.6 dusty
W

Result

Formula

Fixture countN = E × A ÷ (Φ × CU × MF)
Achieved levelN × Φ × CU × MF ÷ A
Power densityN × watts ÷ A
Area per fixtureA ÷ N
Square spacing√(A ÷ N)
SymbolsE lux, A area, Φ lumens, CU utilisation, MF maintenance
50 m² at 300 lx with 3000 lm fixtures, 0.7 utilisation, 0.8 maintenance and 30 W: 8.93 calculated, 9 installed, 302 lx achieved, 270 W total and 5.40 W/m².

Illuminance standards and power density limits

SpaceIlluminance lxPower density W/m²Note
Corridors and stairs1005Emergency lighting at least 5 lx
Bedroom756
Kitchen1006300 lx at the worktop
Office3009General office work
Meeting room3009
Classroom3009500 lx on the blackboard
Retail floor30012Good colour rendering needed
Fine machining500—Set by the process
Operating theatre750—Theatre lamp separate

FAQ

Why does the measured level fall short of design?
Because design values are initial, while luminaires gather dirt and sources age. LEDs lose 20-30% of output in three years and dirty housings another 10-20%, which is what the maintenance factor is for. Plenty of installations pass at handover and measure 60% two years later. Dusty workshops should use 0.6 or even 0.5.
Is more light always better?
No. Beyond what the task needs you get glare, eye strain and wasted energy. Standards grade by task precision: 100 lx in corridors, 300 in offices and classrooms, 500 for fine machining, 750-1000 in operating theatres. Uniformity matters too — the minimum over average should not fall below 0.7, or patchiness proves more tiring than a slightly dim room.
How is power density controlled?
Through efficacy. The same 300 lx needs 20 W/m² with incandescent, 9 with fluorescent and only 5-6 with LED. Codes cap LPD by room type — 9 W/m² for offices, 12 for retail — and exceed it and the job fails sign-off. The right way to cut it is better efficacy and utilisation, through light finishes and good optics, not fewer fixtures and dimmer rooms.

Related calculators

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.