Bored Pile Concrete and Rebar Calculator
Concrete volume, overbreak factor and reinforcement for bored piles.
With the default inputs: Pile diameter 800 · Pile length 20 · Number of piles 20 pcs etc.Total concrete 231.22 m³
Edit the inputs below to recalculate.Inputs
Result
| Volume per pile (theoretical) | 10.053m³ |
| Concrete per pile | 11.561m³ |
| Overbreak volume | 30.16m³ |
| Cage diameter | 700mm |
| Main bars per pile | 592.3kg |
| Spiral length per pile | 219.9m |
| Stirrups per pile | 86.8kg |
| Steel per pile | 679.2kg |
| Total steel | 13.583t |
| Steel ratio | 58.7kg/m³ |
The overbreak factor is actual concrete placed over design volume, covering over-excavation and side collapse, typically 1.1-1.25. Ordering to theoretical volume always runs short, and stopping mid-pour creates a discontinuity. Reinforcement here excludes stiffening rings, anchorage and laps — add 5-8% for actual cutting.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Theoretical volume | π r² L with r = d ÷ 2 |
| With overbreak | volume × K |
| Main bars | 0.00617 × d² × count × length |
| Spiral length | π(D − 2c) × (length ÷ pitch) |
| Stirrup mass | 0.00617 × d² × spiral length |
| Steel ratio | steel ÷ actual volume |
How to work it out
- Theoretical volume per pile = π/4 × D² × L, with D the diameter and L the design length.
- Multiply by the overbreak factor: bored piles run 1.1-1.3 (1.1 in clay, 1.2 in sand, 1.3 in gravel), never 1.0.
- Add the overpour: 0.5-1.0 m above cut-off is laitance and must be broken off, more on long piles; it is paid for but is not pile length.
- Main steel: total length = bars × (pile length + embedment into the pile cap), times unit weight. Embedment is normally 35d-40d.
- Links: spiral length = π(D − 2c + d) × turns × √(1 + (pitch/(π × diameter))²), plus stiffening rings every 2 m.
Where it goes wrong
- Taking the overbreak factor as 1.0 — bored holes enlarge, so 10-30% more concrete goes in than the theoretical volume; at 1.0 the supply runs out mid-pour and the pile breaks.
- Omitting the overpour — 0.5-1.0 m at the head is laitance and contamination that must be broken out; the concrete is wasted but still paid for.
- Measuring links as circumference × turns — a spiral is longer than the circles by 1-3%, and the tightened zones at head and toe need separate treatment.
- Not embedding the main bars in the cap — the pile-to-cap connection is that anchorage, and short embedment wastes the pile.
Material and cost
Bored piles with drilling, cage and concrete 800-1500 CNY/m³, or 600-1200 CNY/m for a φ800. Underwater C30 concrete 480-580 CNY/m³, 15% above normal because of admixtures and higher cement content.
On site
- Underwater concrete needs 180-220 mm slump; stiffer mixes block the tremie, and poor blockage handling breaks the pile.
- Keep tremie embedment between 2 and 6 m — shallower lets water in, deeper and the pipe cannot be withdrawn.
- Do integrity testing at the code frequency and add cross-hole testing on important work; remediation is very expensive.
Basis
- GB 50202-2018 Code for acceptance of foundation construction, Chapter 5 (piles)
- JGJ 94-2008 Technical code for building pile foundations, Chapter 6
- GB 50666-2011 Code for construction of concrete structures, Chapter 7
FAQ
Why can't the overbreak factor be 1.0?
What steel ratio is reasonable for a bored pile?
How does underwater concreting differ?