算BuildCalc

Plaster and Render Calculator

Mortar, cement and sand by layer for internal plastering.

Quick answer

With the default inputs: Plaster area 100 m² · Base coat 12 · Middle coat 6 etc.Total mortar 2.205 m³

Edit the inputs below to recalculate.
SubstrateBase coat mmMiddle coat mmFinish coat mm
Base, middle and finish coats go in separately; beyond 35 mm total you need mesh. Layer thickness controls delamination — thicker is not better.

Inputs

m²
Cement mortar base 10-13
%
kg/m³
About 400 for a 1:3 mix

Result

Total mortar
2.205m³
Total thickness21.0mm
Base coat mortar1.260m³
Middle coat mortar0.630m³
Finish coat mortar0.315m³
Cement882kg
Cement bags18bags
Sand2.25m³
Sand mass3.37t
Mortar per m²0.0221m³/m²

Total plaster thickness is usually 15-20 mm; beyond 25 mm you need mesh or reinforcement or it hollows and cracks. Layering is not about saving material — a single 20 mm coat is heavy enough to shear its own bond. Use 1:3 for the base and 1:2.5 or a gauged mix for the finish; less cement near the face actually trowels better.

Formula

Layer volumearea × thickness ÷ 1000
With wastevolume × (1 + waste%)
Total mortarsum of the layers
Cementtotal × cement content
Sandtotal × 1.02 m³ per m³
Bagsceil(cement ÷ 50)
100 m² at 12 + 6 + 3 mm with 5% waste and 400 kg/m³: 21 mm total, 2.205 m³ of mortar, 882 kg of cement (18 bags) and 2.249 m³ of sand (3.37 t).

How to work it out

  1. Fix the total thickness first: 18 mm for ordinary plastering, 25 mm for high-grade, and anything over 35 mm needs mesh or a reinforced build-up.
  2. Split into coats: base 10-15 mm to bond and level, middle 5-8 mm to level further, finish 2-3 mm for appearance and trowelling. The total is never applied in one pass.
  3. Cost each coat separately: volume = area × that coat's thickness, and the three add up to the total mortar.
  4. Convert by mix: 1:3 or 1:2.5 cement mortar for the base, 1:2.5 or 1:2 for the finish (stronger but shrinks more, so thick finish coats crack); allow about 400 kg of cement per m³.
  5. Add 5-8% waste for droppings, edges and reveals around openings; take the upper figure in rooms with many openings.

Where it goes wrong

Material and cost

Internal plaster at 18 mm with labour 18-30 CNY/m², external 25-40 including mesh and arises. Cement mortar 320-420 CNY/m³, bagged plaster 400-550 CNY/t.

On site

Basis

FAQ

Why three coats instead of one thick one?
Because mortar is plastic before it sets, and a thick coat sags under its own weight and debonds from the background. A single 20 mm coat hollows in over 30% of the area; layers of 6-13 mm applied after the previous has set keep it under 5%. This is not fussiness — it is what passes the tap test at inspection.
Should openings be deducted from plaster area?
Under measurement rules, openings under 0.3 m² are not deducted and larger ones are — but the reveals must be added back. For ordering, leaving them in is closer to reality, because reveals, angles and pipe collars are fiddly and consume more per square metre than flat wall.
How much does the substrate change quantities?
A lot. Fair-faced concrete needs only 15 mm in total, blockwork 20 mm, and rubble or old walls 30 mm or more to level. Absorption matters too: AAC sucks water fast, so it needs a bonding agent and pre-wetting, otherwise the mortar dries before it gains strength and dusts off under a fingernail.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Plaster and Render Calculator. 2026-10-25. https://jianzhujisuan.com/en/plaster-coat

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.