Post-Cast Strip Calculator
Enter strip length, width, slab thickness and waterstop size to get concrete volume plus waterstop length and weight.
With the default inputs: Total strip length 30 · Strip width 0.8 · Slab or wall thickness 0.2 etc.Concrete volume 4.80 m³
Edit the inputs below to recalculate.Inputs
Result
| Waterstop total length | 60.0m |
| Waterstop weight per metre | 7.06kg/m |
| Waterstop weight (incl. waste) | 436.6kg |
| Waterstop area | 18.0m² |
| Formed area | 12.0m² |
Covers the strip itself only, excluding interface scabbling, cleaning, rebar derusting and the premium for shrinkage-compensating concrete. Post-cast strips normally use one grade higher plus an expansive admixture.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Concrete volume | V = total length × width × thickness |
| Waterstop length | L = total length × number of lines |
| Weight per metre | g = width(m) × thickness(m) × 7850 (kg/m) |
| Total weight | W = L × g × (1 + waste %) |
How to work it out
- Concrete volume = total strip length × width × slab or wall thickness, as a net figure.
- Post-cast strip concrete is normally one grade above the adjacent work and shrinkage-compensating, with its own mix design.
- Waterstop length = strip length × number of runs. Typically one in a base slab, one or two in walls and roof slabs.
- Steel weight per metre = width (m) × thickness (m) × 7,850; a 300×3 strip is 7.065 kg/m.
- Add 3% waste: corners, lap welds and junctions with columns and walls all require cut pieces.
Where it goes wrong
- Ordering the waterstop at the theoretical strip length — corners, tees and crossings with reinforcement need cutting or folding, adding 8-15% in practice.
- Ignoring the closure period — settlement strips wait until the structure is complete and settlement has stabilised (generally 60 days or more), shrinkage strips 42 days. Getting this wrong wrecks the finishes sequence.
- Using the same grade as the parent concrete — the old-new interface is the weak plane; it needs one grade up plus an expansive agent, or it will crack and leak.
Material and cost
Strip concrete costs 60-120 per m³ more than normal (higher grade plus expansive agent). A 300×3 waterstop is about 12-18 per metre fabricated, plus 15-25 per metre to weld and fix. The formwork and props must stay in place throughout, and that cost is routinely left out of the estimate.
On site
- Keep strips clear of beam-column joints and highly stressed zones; the usual location is within the middle third of a span.
- Before closure, scabble, wash and remove laitance — poor interface preparation is the leading cause of leakage.
- Support and form the strip independently; striking and re-propping lets the structure on both sides move first.
Basis
- GB 50666-2011 Code for construction of concrete structures, Section 8.3 (post-cast strips and construction joints)
- GB 50108-2008 Technical code for waterproofing of underground works, Chapter 5 (waterproofing at post-cast strips)
- GB 50208-2011 Code for acceptance of waterproofing of underground works, Chapter 4
FAQ
Why must the waterstop flange face the water side?
When can the post-cast strip be poured?
Waterstop plate or swelling strip?