算BuildCalc

Prestress Elongation Calculator

Control stress, length and duct friction give elongation and loss.

Quick answer

With the default inputs: Control stress σcon 1395 MPa · Tensile strength fpk 1860 MPa · Area per tendon 140 mm² etc.Theoretical elongation 206.0 mm

Edit the inputs below to recalculate.
Length LΦ d
Tendon length runs from jack to fixed end; for two-end stressing take half the total.

Inputs

MPa
Strand is usually 0.70-0.75 fpk, i.e. 1302-1395 MPa
MPa
1860 MPa for φs15.2 strand
mm²
140 mm² for φs15.2, 98.7 mm² for φs12.7
pcs
m
Half the total length when stressed from both ends
MPa
195000 MPa for strand, 200000 for rolled bar
1/m
0.0015 for corrugated duct, 0.0015-0.0025 for pulled cores
0.20-0.25 for bonded duct, 0.09-0.12 unbonded
rad
Cumulative angle from the jacking end; zero for straight
mm
4-6 mm for wedge anchors

Result

Theoretical elongation
206.0mm
Jacking force781.2kN
kx + μθ0.0825
Average tension749.8kN
Friction loss4.0%
Theoretical elongation206.0mm
Less anchor set5mm
Site control elongation201.0mm
Elongation per metre6.87mm/m
Stress ratio σcon ÷ fpk75.0%

Elongation is the only check that catches prestressing faults on the spot: if measured and theoretical values differ by more than ±6%, stop and investigate — blocked ducts, wire slip, faulty gauges, short jacking force. Average tension uses Pp = P·(1 − e^−(kx+μθ)) ÷ (kx+μθ), which is exactly the force eaten by duct friction. For two-end stressing take half the length and add both readings before comparing. Anchor set affects the effective prestress at the live end, not the theoretical elongation. Keep σcon at or below 0.75 fpk — beyond that the strand yields, elongation stops being linear and losses after release become large.

Formula

Jacking forceP = σcon × area × strands
Friction termkx + μθ = k × length + μ × angle
Average tensionPp = P × (1 − e^−(kx+μθ)) ÷ (kx+μθ)
ElongationΔL = Pp × length ÷ (area × strands × Ep)
Control valueΔL = ΔL − anchor set
ToleranceMeasured within ±6% of theoretical
Four φs15.2 strands (140 mm²) at 1395 MPa over 30 m with θ = 0.15 rad, k = 0.0015 and μ = 0.25: 781.2 kN jacking force, kx+μθ = 0.0825, 4.0% friction loss, 749.8 kN average tension, 206.0 mm theoretical elongation and 201.0 mm after 5 mm of anchor set.

How to work it out

  1. Jacking force P = σcon × nominal area per strand × strands per tendon, with σcon typically 0.75 fpk.
  2. Friction exponent kx + μθ: k the wobble coefficient (0.0015 per m for duct), μ the friction coefficient (0.20-0.25), θ the angular change in radians.
  3. Mean force Pp = P × (1 − e^−(kx+μθ)) ÷ (kx+μθ); where kx+μθ is below 0.1, take P directly.
  4. Theoretical elongation ΔL = Pp × L ÷ (Ap × n × Ep), with the denominator using the full tendon area and modulus.
  5. Hold measured against theoretical within ±6%; outside that, investigate friction values, duct alignment and the measured modulus.

Where it goes wrong

Material and cost

Strand runs 5,000-6,000 per tonne, anchors 60-150 per set, ducts 8-15 per metre. Equipment calibration costs 2,000-4,000 and is required every six months or 2,000 operations.

On site

Basis

FAQ

Why check elongation and not just gauge pressure?
A gauge only shows jack output, not whether the force reached the far end. With a blocked duct the jack still reaches design pressure while the strand barely moves — friction and the blockage absorb everything; wire slip at the anchor behaves the same way. Elongation infers actual force from the steel's own deformation, so both must agree. Codes require measured elongation within ±6% of theoretical, and any deviation must be investigated, not just topped up.
How does elongation work with two-end stressing?
Single-end: use the full length from jack to fixed end. Two-end: each jack covers half, so compute elongation on half the length, add both readings and compare with the theoretical value for the full length (or compare each end against the half-length value). Stressing from both ends halves the friction loss and is mandatory for long or curved tendons.
What if friction loss is too high?
Three levers: cut μ and k (plastic instead of galvanised ducts, smooth bore, denser chairs so the duct cannot deform); shorten the stressed length — curve over 25-30 m should be stressed from both ends; and flatten the alignment to avoid sharp bends. If calculated loss exceeds 15%, the profile or ducting is wrong: report it rather than jacking harder, because extra force overstresses the live end and can crush the concrete under the anchor.
Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.