Rebar Lap Length Calculator
Lap length ll / llE by splice percentage, plus the permitted number of splices.
With the default inputs: Bar grade HRB400 · Bar diameter 20 · Concrete class C30 etc.Lap length ll 990 mm
Edit the inputs below to recalculate.Inputs
Result
| Anchorage la | 705mm |
| Splice factor ζl | 1.4 |
| Seismic factor | 1.00 |
| Calculated lap | 987mm |
| In bar diameters | 49.3d |
| Permitted splices | 5bars |
| Stagger distance | 1300mm |
Calculated to GB 50010, with a 300 mm minimum. Tied splices in beams should not exceed 25% of the section and in columns 50%. Members in axial or small-eccentricity tension must not use tied laps at all.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Anchorage | la = α × (fy ÷ ft) × d |
| Lap length | ll = ζl × la × ζaE |
| Splice factor | 1.2 up to 25%, 1.4 at 50%, 1.6 at 100% |
| Permitted splices | n = floor(total bars × percentage) |
| Minimum | ll not less than 300 mm |
Lap length ll for HRB400 (mm, 50% spliced, non-seismic)
| Bar | C25 | C30 | C35 | C40 |
|---|---|---|---|---|
| HRB400 Φ12 | 670 | 595 | 540 | 500 |
| HRB400 Φ14 | 780 | 695 | 630 | 580 |
| HRB400 Φ16 | 890 | 790 | 720 | 665 |
| HRB400 Φ18 | 1005 | 890 | 810 | 745 |
| HRB400 Φ20 | 1115 | 990 | 900 | 830 |
| HRB400 Φ22 | 1225 | 1090 | 990 | 910 |
| HRB400 Φ25 | 1390 | 1235 | 1125 | 1035 |
How to work it out
- Establish the basic anchorage length la (or lab from the tables), then look at the splice percentage.
- Lap length ll = ζl × la, with ζl = 1.2 for 25% or less, 1.4 for 50%, 1.6 for 100%.
- In seismic design multiply by ζaE: 1.15 for grades 1 and 2, 1.05 for grade 3, 1.00 for grade 4.
- Take ll as not less than 300 mm.
- Permitted spliced bars n = ⌊total bars × percentage⌋ within one splice zone.
Where it goes wrong
- Using a round figure like 35d or 40d — lap length varies with concrete grade, bar grade, percentage and seismic level, so a fixed multiple fails somewhere.
- Confusing a lap with an anchorage — a lap transfers force between two bars, an anchorage develops one bar into concrete, and the factors differ; a lap is always longer than a bare anchorage.
- Splicing more than 50% at one section — exceeding the permitted tension percentage is a hidden serious defect; a full row of lapped bottom bars turns the beam into a hinge.
Material and cost
Lapping is the cheapest connection type, costing only extra steel. A mechanical coupler runs 8-20 each and a welded splice 5-15. But laps crowd the section and hinder placing, so bars of 25 mm and above usually go mechanical.
On site
- Tighten stirrups through the splice zone (typically ≤5d and ≤100 mm); this is a mandatory seismic requirement.
- Stagger adjacent laps by 1.3ll; without that offset the percentage calculation is meaningless.
- ll and la are different numbers — if the drawing gives llE, cut to llE rather than converting back.
Basis
- GB 50010-2010 Code for design of concrete structures, Section 8.4 (bar connections)
- 16G101-1 Standard drawings for flat-slab detailing, pages 60-61
- GB 50666-2011 Code for construction of concrete structures, Section 5.4
FAQ
Why does a higher splice percentage mean a longer lap?
Why are hoops tightened over a lap?
When are tied laps not permitted?