Rebar Stock Cutting Calculator
Segments, offcut, purchase quantity and utilisation.
With the default inputs: Required length 3.5 · Pieces required 500 pcs · Stock length 12 m etc.Stock bars to buy 167 bars
Edit the inputs below to recalculate.Inputs
Result
| Segments per bar | 3strips |
| Offcut per bar | 1.50m |
| Utilisation | 87.3% |
| Total stock length | 2004m |
| Stock weight | 4.95t |
| Finished weight | 4.32t |
| Waste weight | 0.63t |
Utilisation = finished length ÷ purchased stock length. Offcuts that can serve other locations (stools, ties, short stirrups) lift the real figure, so pool offcuts by size before ordering. Stock choice matters: 3.5 m pieces on 12 m stock give 3 per bar with 1.5 m left; on 9 m stock only 2 with 2 m left, which is worse. For large volumes, run combined patterns on one bar.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Segments = floor((stock + kerf) ÷ (need + kerf)) | |
| Offcut = stock − n×need − (n−1)×kerf | |
| Bars to buy = ceil(pieces ÷ segments) | |
| Utilisation = finished length ÷ (bars × stock) |
How to work it out
- Pieces per stock length: k = ⌊stock length ÷ required length⌋.
- Stock bars required = ⌈pieces required ÷ k⌉.
- Utilisation = (k × required length) ÷ stock length × 100%; the remainder is offcut.
- Total weight = stock bars × stock length × 0.00617 × d².
- Allow for cut loss: 3-5 mm per abrasive cut and 5-8 mm per flame cut, which adds up over thousands of pieces.
Where it goes wrong
- Dividing the requirement by stock length — three 3.5 m pieces from 12 m leaves a 1.5 m offcut, so utilisation is 87.5%, not 100%.
- Ignoring offcut reuse — if the 1.5 m piece serves stirrups, chairs or ties elsewhere, real utilisation exceeds 95%, and that is the whole point of optimising.
- Omitting kerf loss — 500 cuts at 5 mm is 2.5 m, about 6 kg at Φ20: small, but it accumulates into an unexplained shortfall.
Material and cost
Steel runs 4,200-5,000 per tonne, so every 5% cut from the offcut rate is 5% off the material bill. On a 1,000 t project that is 210,000-250,000. Centralised cutting optimisation is the most direct saving in bar fabrication.
On site
- Schedule large diameters and long pieces first, then short pieces into the offcuts.
- Cut for the whole building rather than floor by floor; cross-floor reuse of offcuts saves 3-8%.
- Tag and rack offcuts by size, or they might as well not exist.
Basis
- GB 50666-2011 Code for construction of concrete structures, Section 5.3 (bar fabrication)
- GB/T 1499.2-2018 Steel for reinforced concrete, Part 2: hot-rolled ribbed bars (stock lengths and tolerances)
- GB 50204-2015 Code for acceptance of concrete structures
FAQ
Why is longer stock more efficient?
Can offcuts be counted as usable material?
Why count kerf loss?