Roof Slope Layer Calculator
Average thickness and volume from span and slope.
With the default inputs: Slope span to gutter 12 · Design slope 2% · Minimum thickness 30 etc.Average thickness 150 mm
Edit the inputs below to recalculate.Inputs
Result
| Rise over span | 240mm |
| Maximum thickness at gutter | 270mm |
| Volume | 15.00m³ |
| Bulk density | 800kg/m³ |
| Total mass | 12.00t |
| Added dead load | 1.18kN/m² |
Using half the triangular section - minimum thickness plus span × slope ÷ 2 - is the standard take-off method. Two things are easily missed: the self-weight is significant (150 mm average perlite mortar is about 1.2 kN/m² and must be added to dead load), and the thickness at the gutter is nearly twice the average, so local slab loading and edge formwork must be checked against the maximum. Design slopes are typically 2-3% for structural falls.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Average = min thickness + span × slope ÷ 2 | slope in percent |
| Maximum = min + span × slope | at the gutter |
| Volume = area × average thickness | divide mm by 1000 |
| Added dead load = thickness × density |
How to work it out
- Measure the slope span: the horizontal distance from the ridge or high point to the gutter or outlet, not the sloped length. Where the gutter falls both ways, use one side.
- Fall = span × gradient. A 2% fall over 12 m gives 240 mm of rise.
- Average thickness = minimum thickness + fall ÷ 2. This is the core formula, because thickness varies linearly and the mean sits at mid-span.
- Volume = roof area × average thickness, with the area taken on plan to match the span convention.
- Convert to weight by density: cement mortar 20 kN/m³, expanded clay concrete 8-12, aerated concrete chips 6-8.
Where it goes wrong
- Multiplying the minimum thickness by the area — over 12 m at 2% with a 30 mm minimum the average is 150 mm; using 30 mm gives a fifth of the material.
- Treating the gradient as an angle — 2% is 20 mm per metre, not 2°; 2° is about 3.5%, so the two differ by 75%.
- Using the sloped length as the span — the span is the horizontal projection and the slope is longer, which overstates the fall.
- Computing a four-way fall as one-way — with falls to a central outlet both directions slope, so check both and take the greater average thickness.
Material and cost
Cement mortar slope with labour 30-55 CNY/m² at 50 mm average, expanded clay concrete 45-80, lightweight aggregate 40-70. Cement 400-500 CNY/t, expanded clay 200-350 CNY/m³.
On site
- A levelling screed goes over the slope layer; its rough surface will puncture membrane if covered directly.
- Below 2% fall (inverted roofs, for example) drainage relies on a drainage board and denser outlets, not on the slope.
- Gutters need at least 1% longitudinal fall running to the outlet, with no backfall where water can stand.
Basis
- GB 50345-2012 Technical code for roof engineering, Section 4.3
- GB 50207-2012 Code for acceptance of roof works, Chapter 4
- GB 50854-2013 Code for measurement of building works, Appendix J
FAQ
Why average thickness instead of the minimum?
Structural fall or screed fall?
What goes wrong with a thick fall layer?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Roof Slope Layer Calculator. 2026-10-25. https://jianzhujisuan.com/en/roof-slope-layer