Scaffolding Calculator

Enter the wall perimeter and scaffold height to get the area plus tube, coupler and board quantities.

Quick answer

With the default inputs: Wall perimeter 80 · Scaffold height 20 · Scaffold type Double-row external etc.Scaffold area 1600.0 m²

Edit the inputs below to recalculate.
Length LWidth W
Measured on the vertical elevation of the facade; openings are usually not deducted.

Inputs

Measured around the outside face of the walls
Ground to eaves or parapet top
kg/m²
Typically 4-6 kg/m² for double-row, including standards, ledgers and bracing

Result

Scaffold area
1600.0m²
Lifts @1.8 m12lifts
Scaffold area1600.0m²
Steel tube8.00t
6 m tubes359bars
Couplers2,880pcs
Scaffold boards448.0m²
Safety netting1680.0m²
Wall ties108pcs

Tube assumes Φ48×3.0 at 3.84 kg/m. The scaffold design must be prepared to JGJ 130 by a qualified engineer.

Formula

Scaffold areaA = perimeter × height
Steel tubeW = A × kg per m² × type factor
CouplersN ≈ A × 1.8
BoardsA_board ≈ A × 0.28
Liftslifts = ceil(height ÷ 1.8)
An 80 m perimeter at 20 m high: 1,600 m² of scaffolding, 8 t of tube at 5 kg/m², roughly 2,880 couplers and 448 m² of boards.

How to work it out

  1. Measure the outer face line of the external wall — not the building perimeter and not the grid line. Balconies, canopies and projecting eaves are measured on their own outer face.
  2. Set the height: external ground level to the underside of the eaves; up to the top of the parapet where there is one; to the eaves, not the ridge, on pitched roofs.
  3. Scaffold area = outer face length × height. Openings and balconies are not deducted — this is where scaffold measurement differs fundamentally from floor area.
  4. Take steel content by system: double scaffold 4-6 kg/m², single 3-4, full hall 8-12. The figure already covers standards, ledgers, bracing and base rails.
  5. Total steel = area × content; couplers at 15-20% of steel mass or 1.5-2 per m²; decking by laid area, normally one working lift plus one protective lift.

Where it goes wrong

Material and cost

Scaffold complete (tube and coupler hire plus erection and dismantling) 20-45 CNY/m², including netting and decking. Tube hire about 4-6 CNY/m per month, couplers 0.3-0.5 each per month.

On site

Basis

FAQ

Is scaffold area measured on the wall face or the projection?
External scaffolding is the outside perimeter multiplied by the scaffold height, which is the vertical projection of the wall. Openings are not deducted. Single-row scaffolds count at half rate, internal scaffolds by wall projection, and full-hall scaffolds by internal floor area.
When must a double-row scaffold be used?
Single-row scaffolding is limited to 24 m and only where the wall can take reliable ties. Above 24 m a double-row system is required. In China, ground-supported tube scaffolding at 24 m or more is classified as high-risk work needing an expert-reviewed method statement, and above 50 m cantilevered or climbing systems must be used.
Where does 4-6 kg/m² of tube come from?
Empirical content for a double-row scaffold at 1.8 m lift and 1.5 m bay, including standards, ledgers, transoms, bracing and base rails, works out at roughly 4-6 kg of tube and 1.5-2 couplers per square metre of elevation. Netting, boards and toe boards are counted separately.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Scaffolding Calculator. 2026-10-25. https://jianzhujisuan.com/en/scaffolding

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.