Line-of-Balance Duration Calculator

Rhythmic flow duration with overlap and break adjustments.

Quick answer

With the default inputs: Sections m 4 strips · Processes n 3 pcs · Cycle time t 3 days etc.Total duration 18.0 days

Edit the inputs below to recalculate.

Inputs

strips
How many sections the work is split into
pcs
e.g. fix, form, pour
days
Days one crew spends in one section
days
days
Curing or standing time required

Result

Total duration
18.0days
Base duration18.0days
Technical break0.0days
Overlap deducted0.0days
Sections m4strips
Processes n3pcs
Cycle time3.0days
Crews working at once3pcs
First section complete9.0days
Last section starts9.0days

Rhythmic flow assumes every process takes the same time in every section, which rarely holds — in practice you set the cycle from the leading trade and vary crew sizes elsewhere. For multiple rhythmic flows, divide the cycle times by their greatest common divisor first; irregular flow needs the cumulative-difference method.

Formula

Rhythmic flowT = (m + n − 1) × t
With breaksT = (m + n − 1) × t + Z − C
Sectionsm, the number of flow sections
Processesn, the sequential trades
Cycle timet, days one crew spends per section
First sectionn × t
Four sections, three processes, a 3-day cycle and no breaks: (4 + 3 − 1) × 3 = 18.0 days — the first section finishes on day 9 and the last section starts on day 9.

How to work it out

  1. Fix three numbers: the number of sections m (how many zones the work is split into), the number of processes n (trades in sequence) and the takt t (days per section per trade).
  2. For rhythmic flow the duration is T = (m + n − 1) × t. This assumes equal takt in every section and process; uneven flow needs a different method.
  3. Add technical delays ΣZ: concrete curing, flood testing of waterproofing and drying of plaster all take fixed time.
  4. Deduct overlaps ΣC where a following trade can start before the previous finishes — Blockwork can begin once the frame reaches the third floor.
  5. Final duration T = (m + n − 1) × t + ΣZ − ΣC, then divide by the productive-day ratio for calendar days.

Where it goes wrong

Material and cost

The value of flow work is programme, not cost: proper flow cuts duration 30-50% against sequential working and reduces idle labour and plant, saving 10-20% of indirect cost.

On site

Basis

FAQ

Why (m + n − 1) × t rather than m × n × t?
Because overlapping is the whole point. m × n × t assumes each trade finishes a section before the next starts anywhere — no flow at all. In reality the first crew moves on and the second follows in behind, so only the first trade has a ramp-up and the last a tail, saving on the order of (n − 1) × (t − 1). The more sections, the bigger the saving over sequential working.
Is more sections always better?
No. More sections improve flow and shorten the programme, but each holds less work, crews move more often, and the face may be too small to hold a crew — efficiency drops. As a rule each section should give a crew two to three days of continuous work; below two days, mobilisation dominates and the real duration exceeds the calculation.
Why is a technical break not part of the cycle time?
Because the crew is idle during a break and produces nothing, whereas the cycle measures actual work. Folding 7 days of curing into the cycle turns a 3-day cycle into 10 and stretches the whole line; the correct treatment is a separate addition to the total, with other trades scheduled through the gap. This is why curing time dominates the programme.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Line-of-Balance Duration Calculator. 2026-10-25. https://jianzhujisuan.com/en/schedule-flow

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.