Line-of-Balance Duration Calculator
Rhythmic flow duration with overlap and break adjustments.
With the default inputs: Sections m 4 strips · Processes n 3 pcs · Cycle time t 3 days etc.Total duration 18.0 days
Edit the inputs below to recalculate.Inputs
Result
| Base duration | 18.0days |
| Technical break | 0.0days |
| Overlap deducted | 0.0days |
| Sections m | 4strips |
| Processes n | 3pcs |
| Cycle time | 3.0days |
| Crews working at once | 3pcs |
| First section complete | 9.0days |
| Last section starts | 9.0days |
Rhythmic flow assumes every process takes the same time in every section, which rarely holds — in practice you set the cycle from the leading trade and vary crew sizes elsewhere. For multiple rhythmic flows, divide the cycle times by their greatest common divisor first; irregular flow needs the cumulative-difference method.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Rhythmic flow | T = (m + n − 1) × t |
| With breaks | T = (m + n − 1) × t + Z − C |
| Sections | m, the number of flow sections |
| Processes | n, the sequential trades |
| Cycle time | t, days one crew spends per section |
| First section | n × t |
How to work it out
- Fix three numbers: the number of sections m (how many zones the work is split into), the number of processes n (trades in sequence) and the takt t (days per section per trade).
- For rhythmic flow the duration is T = (m + n − 1) × t. This assumes equal takt in every section and process; uneven flow needs a different method.
- Add technical delays ΣZ: concrete curing, flood testing of waterproofing and drying of plaster all take fixed time.
- Deduct overlaps ΣC where a following trade can start before the previous finishes — Blockwork can begin once the frame reaches the third floor.
- Final duration T = (m + n − 1) × t + ΣZ − ΣC, then divide by the productive-day ratio for calendar days.
Where it goes wrong
- Forgetting overlaps — frame, blockwork and plaster all overlap in practice, and ignoring that makes the programme 20-40% too long.
- Applying the rhythmic formula to uneven flow — with different takts (rebar 2 days, formwork 3, concrete 1) the formula is meaningless; use the step-and-subtract method for non-rhythmic flow.
- Setting technical delays to zero — 7-14 days of curing is hard time, and leaving it out produces a programme nobody can build.
- Swapping m and n — m is spatial sections, n is processes, and both appear in the formula, so putting them in the wrong places changes the answer.
Material and cost
The value of flow work is programme, not cost: proper flow cuts duration 30-50% against sequential working and reduces idle labour and plant, saving 10-20% of indirect cost.
On site
- Make sections roughly equal in quantity so the takts balance; uneven sections create a bottleneck and lose the benefit.
- Keep sections m at least equal to processes n, otherwise the first trade returns before finishing and there is no flow at all.
- Set the takt from the governing process — the one with most labour or the key machine — and fit the others around it.
Basis
- GB/T 50502-2009 Code for design of construction organisation
- GB 50500-2013 Code of bills of quantities and valuation for construction works
- JGJ/T 121-2015 Technical specification for network planning of construction
FAQ
Why (m + n − 1) × t rather than m × n × t?
Is more sections always better?
Why is a technical break not part of the cycle time?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Line-of-Balance Duration Calculator. 2026-10-25. https://jianzhujisuan.com/en/schedule-flow