Secant Pile Wall Calculator
Spacing, wall length and concrete for a secant-pile cut-off wall.
With the default inputs: Pile diameter 800 mm · Pile length 20 m · Number of piles 50 pcs etc.Total concrete 578.1 m³
Use your own dimensions ↓Inputs
Result
| Effective spacing | 0.650m |
| Wall running length | 32.5m |
| Section area | 0.5027m² |
| Concrete per pile | 11.56m³ |
| Concrete per metre of wall | 17.8m³/m |
How this is worked out
A secant wall is a row of alternating "soft" (unreinforced, slow-set) and "hard" (reinforced) piles. The soft piles are cast first, the hard piles then interlock into them to form a continuous cut-off wall. The overlap is usually 150-250 mm, so spacing = diameter − overlap. Secant walls lose more concrete than plain piles, so the overbreak factor is 1.10-1.20. This tool totals piles × per-pile volume; wall length = spacing × count for cost per metre.
Next up: High Strength Bolt Torque Calculator · Plaster and Render Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Spacing | s = D − overlap |
| Wall length | Lw = s·n |
| Concrete per pile | V₁ = πD²/4·L·(1+overbreak%) |
| Total concrete | V = V₁·n |
| Per metre | v = V / Lw |
Quantities per metre of wall by diameter and overlap (from this page's formulas, 15% overbreak)
| Diameter (mm) | Overlap (mm) | Effective spacing (m) | Piles per metre | Concrete (m³/m) |
|---|---|---|---|---|
| 600 | 150 | 0.450 | 2.22 | 0.723 |
| 800 | 150 | 0.650 | 1.54 | 0.889 |
| 800 | 200 | 0.600 | 1.67 | 0.963 |
| 1000 | 200 | 0.800 | 1.25 | 1.129 |
| 1000 | 250 | 0.750 | 1.33 | 1.204 |
| 1200 | 300 | 0.900 | 1.11 | 1.445 |
The soft pile and the hard pile are not the same pile
| Item | Soft pile (primary) | Hard pile (secondary) |
|---|---|---|
| Reinforcement | None, or a inserted H-section only | Reinforced cage, sized for retained load |
| Concrete | Retarded set, to the design's initial-set time | Normal concrete |
| Role | Bored first; becomes the body the next pile cuts into | Cuts the soft pile to form a continuous cut-off |
| Sequence | Alternate piles, then wait for strength | Bored through the soft pile once it has hardened |
| Main risk | Hole collapse or necking - no body to cut | Deviation misses the interlock and the wall splits |
| Check | Verticality, diameter, position | Verticality, overlap width, watertightness |
Basis
- JGJ 120-2012 — retaining structures for excavations, secant and interlocking pile walls
- JGJ 120-2012 — the reinforcement cage is kept out of the secondary pile so it can be cut
FAQ
How does a secant wall differ from a plain soldier pile wall?
Why is the overbreak factor higher than a plain pile?
Secant piles or a diaphragm wall - which one?
How much overlap should I use, and why not less?
Why does a secant wall use more concrete than the same number of plain piles?
Do the soft piles need reinforcement?