Shotcrete Quantity Calculator
Back-calculate batched volume and material use from rebound.
With the default inputs: Area 100 m² · Design thickness 100 · Location Side wall etc.Concrete to batch 11.76 m³
Edit the inputs below to recalculate.Inputs
Result
| Design volume (net) | 10.00m³ |
| Rebound rate | 15% |
| Volume lost to rebound | 1.76m³ |
| Batched mass | 27.1t |
| Cement required | 4.94t |
| Material wasted | 4.1t |
Rebound is empirical: 10-20% on side walls, 20-30% at the crown, more overhead. It depends on nozzle distance (typically 0.8-1.2 m), incidence angle (perpendicular is best), w/c ratio and grading. Note the design volume is net section while batching must cover rebound - this is the main reason shotcrete costs far more than ordinary concrete. Rebound must never be reused.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Net volume = area × thickness | |
| Batch = net ÷ (1 − rebound) | rebound is a loss, so invert |
| Cement = batch × cement per m³ | |
| Loss = batch − net |
How to work it out
- Net in-place volume = sprayed area × design thickness.
- Set rebound by location: 10-15% for walls, 15-25% for the crown, 20-30% for invert or overhead work. Rebound is the only empirical input here and the largest source of error.
- Mixed volume = net volume ÷ (1 − rebound). It is a division, not an addition: spraying 100 m³ at 20% rebound leaves 80 m³ in place, so 125 m³ is needed.
- Consumption follows the mixed volume: cement, sand, stone and accelerator each scale from it.
- Accelerator dosage is usually 3-5% of cement weight; wet spraying uses less than dry, but the plant costs more.
Where it goes wrong
- Adding rebound instead of dividing by it — 100 m³ net with 20% rebound needs 125 m³, not 120; the mistake leaves material 4% short every time.
- Using one rebound figure for the whole face — crown and wall differ by a factor of two, so an average over-runs the crown and wastes on the wall.
- Ignoring the strength penalty of accelerator — above 5% dosage the 28-day strength drops markedly, and crews chasing lower rebound by overdosing fail the strength test.
Material and cost
Wet-mix sprayed concrete runs 550-850 per m³ all in (labour, plant, accelerator, rebound), dry-mix 450-700 with higher rebound and dust. Every 5% cut in rebound saves 40-70 per m³.
On site
- Hold the nozzle 0.8-1.2 m from the surface and square to it; angling off the normal raises rebound immediately.
- Spray in 50-100 mm layers, wall footing first and crown last; a thick single pass slumps off under its own weight.
- Never reuse rebound — the aggregate has segregated and the cement has hydrated, so strength falls.
Basis
- GB 50086-2015 Technical code for ground anchor and shotcrete support (rebound and execution)
- JGJ/T 372-2016 Technical specification for application of sprayed concrete
- GB 50204-2015 Code for acceptance of concrete structures (strength and thickness testing)
FAQ
Why is crown rebound so much higher than side wall?
Can rebound be reused?
How much do nozzle distance and angle matter?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Shotcrete Quantity Calculator. 2026-10-25. https://jianzhujisuan.com/en/shotcrete-quantity