Slope Converter
Enter rise and run to get the slope as a percentage, in degrees, as a ratio and as rise per metre.
With the default inputs: Rise 1 · Run 10Slope 10.00%
Edit the inputs below to recalculate.Inputs
Result
| Percentage | 10.00% |
| Angle | 5.71° |
| Ratio | 1 : 10.00 |
| Rise per metre | 100.0mm/m |
| Slope length | 10.050m |
| Per mille | 100.0‰ |
Slope = rise ÷ run, independent of slope length. Always set out using horizontal distance, not a length measured along the slope.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Slope | i = rise ÷ run |
| Percentage | slope % = i × 100 |
| Angle | θ = arctan(i) |
| Ratio | 1 : n where n = 1 ÷ i |
| Slope length | L = √(rise² + run²) |
Slope conversion table
| Slope | Angle | Ratio | Rise per metre | Typical use |
|---|---|---|---|---|
| 0.5% | 0.29° | 1:200 | 5 mm | Surface drainage |
| 1% | 0.57° | 1:100 | 10 mm | Gutters and eaves |
| 2% | 1.15° | 1:50 | 20 mm | Flat roof falls |
| 3% | 1.72° | 1:33.3 | 30 mm | Structural falls |
| 5% | 2.86° | 1:20 | 50 mm | Profiled metal roofs |
| 10% | 5.71° | 1:10 | 100 mm | Max. accessible ramp |
| 20% | 11.31° | 1:5 | 200 mm | Asphalt shingle roofs |
| 33% | 18.26° | 1:3 | 330 mm | Plain tile roofs |
| 50% | 26.57° | 1:2 | 500 mm | Steep pitched roofs |
| 100% | 45.00° | 1:1 | 1000 mm | 45° pitched roof |
How to work it out
- Confirm what the rise and the run each mean. Rise is the level difference between two points; run is the horizontal projection, not the length measured along the slope. Confusing these three is the leading cause of slope errors.
- Base gradient i = rise ÷ run. One metre of rise over ten metres of run gives i = 0.1.
- As a percentage: i × 100% = 10%. That is what a stated 2% fall means — 2 m of rise per 100 m of horizontal run.
- As an angle: θ = arctan(i). At i = 0.1 the angle is 5.71°, not 10°. Percentage and angle are close at shallow gradients but diverge rapidly beyond about 15%.
- As a ratio 1 : n, where n = 1 ÷ i. So i = 0.1 is 1 : 10. The 1:12 required for accessible ramps is i = 0.0833, or 8.33%.
- Slope length = √(rise² + run²), used for ramp finishes, roof tiles and inclined pipe runs.
Where it goes wrong
- Reading a percentage as an angle. A 10% gradient is 5.71°, not 10°; a 20% gradient is 11.3°, still not 20°. This is the most widespread confusion on site.
- Using the slope length as the run. The slope length is longer, so the computed gradient comes out low. With 3 m rise over 10 m run the true figure is 30%, but using the 10.44 m slope gives 28.7%.
- Designing a 2% roof fall but building it flat. When the fall is formed in screed the thinnest point may be only 20 mm, and the achieved gradient often falls below 1% — which is where ponding comes from.
- Assuming steeper is better for drainage. See the drain slope calculator: over-steep falls separate solids from liquid and block more readily.
- Reading 1:12 for an accessible ramp as 12%. It is 8.33%, and building 12% produces a ramp a wheelchair cannot climb.
Material and cost
The cost of a slope error depends on location: insufficient roof fall causes ponding and leakage, and rectification means stripping membrane and insulation at 150-300 CNY/m²; an under-sloped drain blocks and breaking tiles to fix it runs to hundreds or thousands per location; an over-steep accessible ramp means rebuilding the whole base.
On site
- Gradients worth memorising: structural roof fall 2-3%, bathroom floor fall 1-1.5%, horizontal drainage 0.5-3.5% by diameter, accessible ramp 1:12 (8.33%), vehicle ramps not steeper than 15% on straights, cycle ramps not steeper than 8%.
- Different trades express gradient differently: architecture and drainage use percentages, steel and mechanical use degrees, accessibility and roads use ratios. Check the convention before reading a drawing.
- The practical way to check a fall on site is a spirit level with feeler gauges, or a laser level measuring level difference between two points. Eyeballing cannot distinguish 1% from 3%.
- The direction of fall is more error-prone than the value. State which drain a floor falls to, and draw the watershed lines on drawings with multiple falls.
Basis
- GB 50345-2012 Technical code for roof engineering, roof drainage design
- GB 50763-2012 Code for accessibility design, accessible ramps
- GB 50015-2019 Standard for design of building water supply and drainage, hydraulic calculation
FAQ
Should I use percent or degrees?
What roof slopes are typical?
What is the most common setting-out mistake?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Slope Converter. 2026-10-25. https://jianzhujisuan.com/en/slope-converter