Soil Mixing Wall Calculator
Columns, mixed volume and cement for a three-axis mixing wall.
With the default inputs: Wall length 100 m · Wall depth 18 m · Column diameter 850 mm etc.Cement 556.0 t
Use your own dimensions ↓Inputs
Result
| Spacing | 0.600m |
| Columns | 168bars |
| Mixed volume | 1716m³ |
| Cement ratio | 18% |
| Cement per metre of wall | 5.56t/m |
How this is worked out
SMW (Soil Mixing Wall) uses a three- or twin-axis mixer to blend cement grout with in-situ soil into a continuous wall that both retains and seals, often with H-beams inserted for strength. The cement ratio is cement weight ÷ natural soil weight; soft clay uses 15-20%, lower in sand, higher in silt. Natural density is taken as 1.8 t/m³, so cement = mixed volume × 1.8 × ratio. A triple-axis rig makes three columns per pass; spacing uses diameter − overlap and the overlap is not deducted, so the result is slightly conservative (safe side).
Next up: Soil Nail Wall Calculator · High Strength Bolt Torque Calculator
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Spacing | s = D − overlap |
| Columns | n = ⌈length/s⌉ + 1 |
| Mixed volume | V = n·πD²/4·depth |
| Cement | M = V·1.8·ratio% (t) |
Cement by dosage ratio (100 m long, 18 m deep, 850 mm at 600 mm centres, from this page's formulas)
| Dosage | Total cement (t) | Per metre of wall (t/m) | Per m³ of mixed soil (kg/m³) | Note |
|---|---|---|---|---|
| 12% | 371 | 3.71 | 216 | Low end - granular soil, temporary works |
| 15% | 463 | 4.63 | 270 | Common lower bound |
| 18% | 556 | 5.56 | 324 | The usual value, and this tool's default |
| 20% | 618 | 6.18 | 360 | Common upper bound, tighter cut-off |
| 22% | 680 | 6.80 | 396 | Above the usual range - prove it with a trial panel |
Choosing a cut-off wall (qualitative; cost and depth vary by region and rig)
| Method | Cut-off reliability | Typical depth (m) | Footprint | Slurry / spoil | Where it fits |
|---|---|---|---|---|---|
| SMW mixing wall | Good, continuous | up to 25-30 | Small | Little spoil | Retaining plus cut-off, the workhorse |
| Jet grouting | Fair; joints between columns are the weak point | up to 30 | Small | Much return flow | Tight sites, local repair, spot cut-off |
| Secant pile wall | Very good, also retains | up to 30 | Small | Slurry | Deep, high-spec, close to buildings |
| Diaphragm wall | Best; can be the permanent structure | No practical limit | Large | Large slurry volume | Deep basements, high water table, city centres |
| Sheet piles + seal | Depends on the interlock; leaks | up to 15 | Small | None | Shallow or temporary works, recoverable |
Basis
- JGJ 79-2012 — cement-soil mixing chapter, including the cement ratio and curing requirements
- JGJ 120-2012 — use of mixing walls as a cut-off or as a gravity retaining structure
FAQ
How do I pick the cement ratio?
SMW vs jet grouting - what is the difference?
What cement dosage should I use, and what happens if it is too low?
Triple-axis or double-axis mixing - what is the difference?
Does this tool check the wall's strength and stability?
How long until the mixed soil reaches strength, and how does that drive the programme?