算BuildCalc

Soil Nail Wall Calculator

Nail count and length, grout volume, facing concrete and mesh.

Quick answer

With the default inputs: Wall length 30 · Wall height 6 · Horizontal spacing 1.5 etc.Number of soil nails 80 bars

Edit the inputs below to recalculate.
FaceVertical spacing mNail length m
Nails sit at 1.0-1.5 m vertically and 10-15° downward; their length must pass the potential slip surface, typically 0.6-1.2 times the excavation depth.

Inputs

Vertical height; adjust for battered faces
Usually 0.6-1.0 times the excavation depth
1.2-1.3 in sand, higher in soft or collapsing ground
HRB400 φ22-32 typically
Same both ways, usually 150-250 mm

Result

Number of soil nails
80bars
Wall area180.0m²
Nail grid20 × 4rows
Total nail length480m
Total drilling480m
Grout volume5.70m³
Nail bar weight1851.0kg
Facing concrete18.90m³
Mesh weight469.2kg
Steel per m²12.9kg/m²

This is a quantity take-off only, not a stability check. Whether a soil nail wall stands depends on pull-out capacity, internal and external stability, and must be designed from the ground investigation by a qualified engineer; nail length is usually 0.6-1.0 times the excavation depth, longer in soft ground. Soil nails are unsuitable in mud, muddy soil, loose sand or water-bearing ground, where holes will not stand and grout bodies cannot grip. Facing concrete includes 5% rebound.

Formula

Wall areaA = length × height
Nail countn = ⌈length ÷ h-spacing⌉ × ⌈height ÷ v-spacing⌉
Grout volumeV = π ÷ 4 × hole² × total length × fill factor
Nail bar weightW = total length × dia² × 0.00617
Facing concreteV = A × thickness × 1.05
Mesh weightW = A × metres per m² × dia² × 0.00617
30 m by 6 m at 1.5×1.5 m spacing, 6 m nails in 110 mm holes: 20×4 = 80 nails, 480 m total, 5.70 m³ grout, 1851 kg of bar, 18.9 m³ facing, 469.2 kg of mesh.

How to work it out

  1. Count the nails: horizontal rows = wall length ÷ horizontal spacing, vertical rows = height ÷ vertical spacing, multiplied and rounded up, usually on a staggered or rectangular grid.
  2. Total length = count × length per nail. Lengths normally shorten with depth (the upper rows carry more), so a uniform length undercounts the top and overcounts the bottom.
  3. Grout volume = count × π/4 × hole diameter² × nail length × a filling factor of 1.2-1.3. Grout is what develops the anchorage.
  4. Face concrete = wall area × thickness (80-150 mm), C20 sprayed.
  5. Mesh = wall area × weight per m² (φ6.5 at 200 both ways is about 2.6 kg/m²), plus the bearing bars at each nail head, typically 2φ12 continuous.

Where it goes wrong

Material and cost

Complete soil-nailed wall 180-350 CNY/m² including nails, grout, facing and mesh; nails 60-120 CNY/m. Sprayed concrete 80-150 CNY/m³.

On site

Basis

FAQ

Soil nails versus ground anchors?
Prestress is the essential difference. Anchors are tensioned to actively compress the ground, with bonded and free lengths plus a head; soil nails are passive, fully grouted, and only engage as the soil moves. Soil nail walls therefore tolerate movement — typically 0.1-0.5% of excavation depth — and suit poorly where nearby structures are movement-sensitive. Anchors control movement better but occupy ground beyond the site boundary.
Why is the grout fill factor above 1?
Because the real hole is bigger than the theoretical cylinder: drilling over-breaks, grout penetrates the surrounding sand, and soft ground sloughs and necks before collapsing into voids. Grout always exceeds π/4 × d² × L. Use 1.2-1.3 in sand, 1.25-1.4 in silt, over 1.5 in soft or collapsing strata. A factor above 2 signals voids or grout escape and needs investigation.
What ground suits a soil nail wall?
Silt, sand, gravelly soil and weathered rock above the water table or after dewatering — ground that can be drilled and provides pull-out resistance. It is unsuitable in mud and muddy soil (very low capacity, high creep), loose sand (holes collapse), and un-dewatered ground (grout diluted, holes unstable). Soil nail walls are generally limited to about 12 m depth; deeper needs a special review.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Soil Nail Wall Calculator. 2026-10-25. https://jianzhujisuan.com/en/soil-nail-wall

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.