Soil Haulage Calculator

Natural to loose volume, tonnes and truck loads without overloading.

Quick answer

With the default inputs: Natural volume 100 m³ · Soil type Ordinary soil · Initial bulking Ks 1.2 etc.Total mass 190.00 t

Edit the inputs below to recalculate.

Inputs

m³
In-situ volume from the drawings
Sand 1.1-1.2, clay 1.2-1.3

Result

Total mass
190.00t
Loose volume120.00m³
Natural density1.90t/m³
Loose density1.583t/m³
Truck loads8loads
Mass per load23.75t
Loose volume per load15.00m³
Body volume at 1.1 fill16.50m³
Loads in a 20 m³ body6loads

Always count loads by weight, never by loose volume. At 1.9 t/m³ with Ks 1.2, one cubic metre of soil becomes 1.2 m³ loose weighing 1.9 t; filling a 20 m³ body gives 38 t, a 52% overload. Most tipper accidents and fines come from exactly this mistake.

Formula

Loose volumenatural volume × Ks
Total massnatural volume × natural density
Loose densitynatural density ÷ Ks
Loadsceil(mass ÷ payload)
Loose volume per loadtotal loose ÷ loads
Body volumeper-load loose × 1.1
100 m³ of ordinary soil at Ks 1.2 with 25 t trucks: 120.00 m³ loose, 190.00 t, eight loads at 23.75 t and 15.00 m³ loose each — a 16.50 m³ body.

How to work it out

  1. Separate the three volumes: in-situ (intact, for excavation quantities), loose (loaded, for truck counts) and compacted (after backfill).
  2. Mass = in-situ volume × in-situ density. Mass does not change whether the soil is loose or compact.
  3. Loose volume = in-situ volume × initial bulking factor Ks, typically 1.1-1.3, from 1.1 for class 1 soil to 1.3 for class 4.
  4. Loads: by weight = total mass ÷ payload; by volume = loose volume ÷ body volume. Take the greater, since both overload and overfill are illegal.
  5. Backfill is measured compacted: compacted volume = in-situ volume ÷ final bulking Ks' (1.02-1.05), so slightly more soil is needed than is dug.

Where it goes wrong

Material and cost

Disposal 15-40 CNY/m³ including tip fees, tipper hire 300-800 CNY per load by distance, loading 3-8 CNY/m³. Night working in cities carries a premium.

On site

Basis

FAQ

Why not dispatch by volume?
Because excavation bulks the soil — more volume, same mass — so loading by volume overloads. One cubic metre of soil becomes 1.2 m³ loose at the same 1.9 t: dispatch a truck per 1.2 m³ and each carries only 1.9 t, which is wasteful; fill the 20 m³ body and it is 38 t. Payload is the only measure that works both ways.
Ks or Ks′?
For carting away and loading, use the initial factor Ks — loose over natural — because that is the freshly dug state. For how much soil backfill needs, use Ks′ — compacted over natural. Ks is typically 1.1-1.3 and Ks′ 1.02-1.08; swapping them overstates haulage by 20%, which is a fifth of the carting cost.
Why is construction waste so light?
Because it is full of voids — broken brick, concrete lumps, mortar, timber and packaging mixed together can be 50% air. Waste bulks at 1.4-1.7 t/m³ against 2.4 for solid concrete. Carting is often priced by volume but weighed in tonnes, and that mismatch is a common source of disputes.

Cite this page

Use this format in reports, method statements or coursework. The link is permanent.

Building Calculator. Soil Haulage Calculator. 2026-10-25. https://jianzhujisuan.com/en/soil-ton

Results are estimating aids only and are not a design basis. Construction and final accounts must follow the drawings, the applicable standards and an approved method statement. Anything affecting structural safety, shoring or falsework must be checked by a suitably qualified engineer.