Masonry Tie Bar Calculator
Tie bar count, weight, holes and resin from wall and spacing.
With the default inputs: Wall height 3 · Vertical spacing 500 · Bars per course 2 pcs etc.Total tie bars 12 bars
Edit the inputs below to recalculate.Inputs
Result
| Courses | 6courses |
| Bars per course | 2bars |
| Length per bar | 1000mm |
| Total length | 12.0m |
| Unit weight | 0.222kg/m |
| Total weight | 2.67kg |
| Drilled holes | 12pcs |
| Resin volume | 180ml |
Bars must extend at least one fifth of the wall length and not less than 700 mm, and run continuous in seismic areas. Embedment is typically 15d and pull-out testing is mandatory, at least three bars per inspection lot.
Reverse: known result, work out one input
Enter a target result; the other inputs stay fixed and this one is worked out.
Formula
| Courses | n = floor(height ÷ spacing), at least 2 |
| Total bars | N = courses × bars per course |
| Total length | L = N × length into wall |
| Weight | W = L × 0.00617 × d² |
| Resin | V = N × resin per hole |
How to work it out
- Courses n = ⌊wall height ÷ vertical spacing⌋, minimum two. Spacing is normally 500 mm and must line up with the brick courses.
- Total bars N = courses × bars per course, usually two for a 240 wall and three for 370.
- Total length L = N × embedment length. Embedment by seismic intensity: at least 700 mm and a fifth of the wall length at 6 and 7; at least 1,000 mm and a fifth at 8 and 9.
- Weight = L × 0.00617 × d².
- Resin = N × resin per hole, typically 10-15 ml for an 80 mm deep Φ6 hole.
Where it goes wrong
- Using 1,000 mm everywhere — 6 and 7 need only 700, so a blanket 1,000 wastes 40%; the code minimum still applies.
- Rounding the course count up — it rounds down, since extra courses exceed the wall height and a partial last course takes none.
- Forgetting the end hook — ties usually finish with a 90° hook into the masonry, adding about 6.25d.
Material and cost
Ties are most of the steel in masonry work, at about 0.9 per metre for Φ6. Resin costs 25-40 per 300 ml cartridge, or 3-5 per hole. Ties and resin on 1,000 m² of wall come to roughly 8,000-12,000.
On site
- Where a continuous tie is required (seismic walls), measure it as full length rather than 1,000 mm per course.
- Blow and brush the drilled hole; dust left inside halves the anchorage capacity.
- Bed the tie in the mortar joint, not laid on the brick face — on the face it does nothing.
Basis
- GB 50003-2011 Code for design of masonry structures, Section 6.3 (wall-to-column connection)
- GB 50011-2010 Code for seismic design of buildings, Section 13.3 (non-structural elements)
- GB 50203-2011 Code for acceptance of masonry construction, Chapter 5
FAQ
Must tie bars be resin-anchored?
Why at least two courses per storey?
How is pull-out testing done?
Cite this page
Use this format in reports, method statements or coursework. The link is permanent.
Building Calculator. Masonry Tie Bar Calculator. 2026-10-25. https://jianzhujisuan.com/en/tie-bar